Construction Project Scheduling Optimization with Critical Path Method (CPM) and Precedence Diagram Method (PDM) (Case Study: PT Samara Insan Sentosa)

Delays in construction projects often occur due to suboptimal scheduling, which results in increased costs and decreased efficiency. PT Samara Insan Sentosa faces a similar problem, where the planned project duration does not match the realization in the field. This study aims to optimize project scheduling using the Critical Path Method (CPM) and Precedence Diagram Method (PDM). The research methods used include secondary data analysis, interviews, and scheduling calculations with both methods. The results of the study show that CPM and PDM can identify critical paths and optimize project completion duration. A comparison of the two methods shows that PDM is more flexible than CPM, with a shorter project completion duration. Implementation of the PDM method can reduce project completion time without sacrificing the quality of work. The conclusion of this study is that scheduling optimization using the right method can increase project efficiency and reduce the risk of delays. The impact of this study can help companies improve the effectiveness of project management.

Authors

Publication Details

Journal
Jurnal Sains dan Teknologi Industri
Published
2025-06-30
DOI
https://doi.org/10.24014/sitekin.v22i2.37258
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Construction Project Scheduling Optimization with Critical Path Method (CPM) and Precedence Diagram Method (PDM) (Case Study: PT Samara Insan Sentosa)

Aina Nindiani, Nuke Maheswara Aji, Weni Tri Sasmi, Mohammad Fadli Perdana
Jurnal Sains dan Teknologi Industri
Management and Optimization Techniques
article

Construction Project Scheduling Optimization with Critical Path Method (CPM) and Precedence Diagram Method (PDM) (Case Study: PT Samara Insan Sentosa)

Aina Nindiani, Nuke Maheswara Aji, Weni Tri Sasmi, Mohammad Fadli Perdana
article en

Abstract

Delays in construction projects often occur due to suboptimal scheduling, which results in increased costs and decreased efficiency. PT Samara Insan Sentosa faces a similar problem, where the planned project duration does not match the realization in the field. This study aims to optimize project scheduling using the Critical Path Method (CPM) and Precedence Diagram Method (PDM). The research methods used include secondary data analysis, interviews, and scheduling calculations with both methods. The results of the study show that CPM and PDM can identify critical paths and optimize project completion duration. A comparison of the two methods shows that PDM is more flexible than CPM, with a shorter project completion duration. Implementation of the PDM method can reduce project completion time without sacrificing the quality of work. The conclusion of this study is that scheduling optimization using the right method can increase project efficiency and reduce the risk of delays. The impact of this study can help companies improve the effectiveness of project management.

Jurnal Sains dan Teknologi IndustriVol. 22(2)
Openalex Percentile: Top 65%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Construction Project Scheduling Optimization with Critical Path Method (CPM) and Precedence Diagram Method (PDM) (Case Study: PT Samara Insan Sentosa) — Aina Nindiani, Nuke Maheswara Aji, et al. · Jurnal Sains dan Teknologi Industri (2025) | TGRS Research Map | TGRS