Proposed Scheduling of Preventive Maintenance on Co₂ Welding Machines Based on Reliability Analysis and FMEA Methods at PT. Sub Automotive

As the industry increases its dependence on production machinery, machine maintenance is a vital aspect in ensuring the smooth operation of the company. PT. Sub Automotive, as a dump truck carousel manufacturer, faces the problem of high downtime in CO₂ welding machines caused by component damage. This research aims to design an appropriate preventive maintenance schedule to reduce the frequency of damage and increase machine availability. The methods used include Mean Time Between Failure (MTBF), Mean Time To Repair (MTTR), and Overall Availability (Ao) analysis, as well as the Failure Mode and Effect Analysis (FMEA) approach to identify critical components based on the Risk Priority Number (RPN) value. The results showed an average machine availability value of 97%, exceeding the global standard of 90%. The components with the highest RPN values, namely the Control PCB (180), Nozzle (168), and Contact Tip (126), were identified as the main contributors to downtime. Based on these results, preventive maintenance recommendations were prepared focused on these components to improve the overall reliability of the system

Authors

Publication Details

Journal
Jurnal Sains dan Teknologi Industri
Published
2025-06-30
DOI
https://doi.org/10.24014/sitekin.v22i2.37605
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Proposed Scheduling of Preventive Maintenance on Co₂ Welding Machines Based on Reliability Analysis and FMEA Methods at PT. Sub Automotive

Ade Suhara, Roban Roban, Muhamad Sayuti, Rizko Umar Dana
1 links
Jurnal Sains dan Teknologi Industri
Management and Optimization Techniques
article

Proposed Scheduling of Preventive Maintenance on Co₂ Welding Machines Based on Reliability Analysis and FMEA Methods at PT. Sub Automotive

Ade Suhara, Roban Roban, Muhamad Sayuti, Rizko Umar Dana
article en

Abstract

As the industry increases its dependence on production machinery, machine maintenance is a vital aspect in ensuring the smooth operation of the company. PT. Sub Automotive, as a dump truck carousel manufacturer, faces the problem of high downtime in CO₂ welding machines caused by component damage. This research aims to design an appropriate preventive maintenance schedule to reduce the frequency of damage and increase machine availability. The methods used include Mean Time Between Failure (MTBF), Mean Time To Repair (MTTR), and Overall Availability (Ao) analysis, as well as the Failure Mode and Effect Analysis (FMEA) approach to identify critical components based on the Risk Priority Number (RPN) value. The results showed an average machine availability value of 97%, exceeding the global standard of 90%. The components with the highest RPN values, namely the Control PCB (180), Nozzle (168), and Contact Tip (126), were identified as the main contributors to downtime. Based on these results, preventive maintenance recommendations were prepared focused on these components to improve the overall reliability of the system

Jurnal Sains dan Teknologi IndustriVol. 22(2)
Openalex Percentile: Top 65%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.