Safety Risk Management in China’s Power Engineering Construction: Insights and Countermeasures from the 14th Five-Year Plan

Power engineering construction serves as the cornerstone of modern social development. Against the backdrop of new power system development, this study employs field investigations, case analysis, and expert discussions to conduct an in-depth analysis of the current status, existing problems, and characteristics of safety risk control in China’s power engineering construction during the 14th Five-Year Plan period. Through systematic analysis of 59 accident cases, 66 distinct causes are identified across 14 categories. Chi-squared testing quantitatively determines the top three risk factors: hollowing out of construction units’ own workforce (χ2 = 10.22), deficiencies in risk classification and hierarchical implementation (χ2 = 9.0), and inadequate hazard identification (χ2 = 6.25). Through brainstorming and expert discussions, 11 critical risks in China’s power engineering construction have been identified, and a set of countermeasures has been formulated. These include nine enterprise-level initiatives such as deepening engineering procurement construction management, improving training systems, optimizing bidding methods, and implementing management principles, along with four regulatory measures targeting the National Energy Administration of China and its regulatory agencies. This study innovates by combining quantitative chi-squared analysis with expert-derived countermeasures, offering a model for transitioning economies. While the sample size imposes limitations on generalizability, this research can significantly improve the intrinsic safety management level of power construction enterprises in China and provides valuable reference experience for similar transitioning countries developing energy infrastructure.

Authors

Institutions

Publication Details

Journal
Processes
Published
2025-08-31
DOI
https://doi.org/10.3390/pr13092789
Citations
1
Primary Topic
Risk and Safety Analysis
Type
article
Field-Weighted Citation Impact
1.40
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Safety Risk Management in China’s Power Engineering Construction: Insights and Countermeasures from the 14th Five-Year Plan

Fan Hu, Yi Xiang, Jingyi Zhao, Li Chen et al.
1 citations
Processes
Risk and Safety Analysis
1.40
article

Safety Risk Management in China’s Power Engineering Construction: Insights and Countermeasures from the 14th Five-Year Plan

Fan Hu, Yi Xiang, Jingyi Zhao, Li Chen, Zhu Xiao-li
article en
1 citations

Abstract

Power engineering construction serves as the cornerstone of modern social development. Against the backdrop of new power system development, this study employs field investigations, case analysis, and expert discussions to conduct an in-depth analysis of the current status, existing problems, and characteristics of safety risk control in China’s power engineering construction during the 14th Five-Year Plan period. Through systematic analysis of 59 accident cases, 66 distinct causes are identified across 14 categories. Chi-squared testing quantitatively determines the top three risk factors: hollowing out of construction units’ own workforce (χ2 = 10.22), deficiencies in risk classification and hierarchical implementation (χ2 = 9.0), and inadequate hazard identification (χ2 = 6.25). Through brainstorming and expert discussions, 11 critical risks in China’s power engineering construction have been identified, and a set of countermeasures has been formulated. These include nine enterprise-level initiatives such as deepening engineering procurement construction management, improving training systems, optimizing bidding methods, and implementing management principles, along with four regulatory measures targeting the National Energy Administration of China and its regulatory agencies. This study innovates by combining quantitative chi-squared analysis with expert-derived countermeasures, offering a model for transitioning economies. While the sample size imposes limitations on generalizability, this research can significantly improve the intrinsic safety management level of power construction enterprises in China and provides valuable reference experience for similar transitioning countries developing energy infrastructure.

ProcessesVol. 13(9)
China University of Geosciences (CN), Wuhan Research Institute of Materials Protection (CN), Huazhong University of Science and Technology (CN)
Openalex Percentile: Top 13%
Risk and Safety Analysis
1.40
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.