Collaborative Management of Quality, Schedule, and Cost in Low-Altitude Economic Infrastructure Construction Projects

This paper focuses on low-altitude economic infrastructure construction projects, constructs a collaborative management model for quality, schedule, and cost, and conducts case studies. Data analysis of the Jiangbei General Airport and Jiangnan Low-Altitude Communication Network projects reveals that under the traditional management model, the quality inspection pass rates for these two projects were only 82.3% and 79.5%, respectively, with cost overruns of 14.2% and 18.7%. Data simulations demonstrate that the collaborative management model can increase the quality-schedule-cost coupling coefficient to 0.87 and reduce the delay rate at key nodes by over 35%. In case application, the quality pass rate for Case A increased to 98.7%, while cost overruns were reduced to 3.8%. In Case B, communication latency was stabilized at 42ms, and the approval cycle was shortened by 67%. This research demonstrates that the model can effectively address management challenges and provide a scientific management paradigm for low-altitude economic infrastructure construction.

Authors

Institutions

Publication Details

Journal
Scientific journal of economics and management research.
Published
2025-08-27
DOI
https://doi.org/10.54691/41fvcg93
Primary Topic
Air Traffic Management and Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Collaborative Management of Quality, Schedule, and Cost in Low-Altitude Economic Infrastructure Construction Projects

Yili Wang, Dan Wang, Yunbo Zhang
Scientific journal of economics and management research.
Air Traffic Management and Optimization
article

Collaborative Management of Quality, Schedule, and Cost in Low-Altitude Economic Infrastructure Construction Projects

Yili Wang, Dan Wang, Yunbo Zhang
article en

Abstract

This paper focuses on low-altitude economic infrastructure construction projects, constructs a collaborative management model for quality, schedule, and cost, and conducts case studies. Data analysis of the Jiangbei General Airport and Jiangnan Low-Altitude Communication Network projects reveals that under the traditional management model, the quality inspection pass rates for these two projects were only 82.3% and 79.5%, respectively, with cost overruns of 14.2% and 18.7%. Data simulations demonstrate that the collaborative management model can increase the quality-schedule-cost coupling coefficient to 0.87 and reduce the delay rate at key nodes by over 35%. In case application, the quality pass rate for Case A increased to 98.7%, while cost overruns were reduced to 3.8%. In Case B, communication latency was stabilized at 42ms, and the approval cycle was shortened by 67%. This research demonstrates that the model can effectively address management challenges and provide a scientific management paradigm for low-altitude economic infrastructure construction.

Scientific journal of economics and management research.Vol. 7(8)
Guangzhou Vocational College of Science and Technology (CN)
Openalex Percentile: Top 69%
Air Traffic Management and Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Collaborative Management of Quality, Schedule, and Cost in Low-Altitude Economic Infrastructure Construction Projects — Yili Wang, Dan Wang, et al. · Scientific journal of economics and management research. (2025) | TGRS Research Map | TGRS