OPTIMIZING PROJECT SCHEDULING USING CPM AND PERT METHODS (CASE STUDY: PEJAMBON 8-STOREY FLAT, CENTRAL JAKARTA)

Pejambon 8 Storey-Flat Construction Project is one of the annual work programs through the allocation of Government Islamic Securities (SBSN) funding for the 2023 Ministry of Finance of the Republic of Indonesia. In this research, the CPM and PERT planning methods were used to implement project time management and increase effectiveness, by making schedules empirically. The aim of applying the CPM and PERT methods is to compare expectations with actual progress and avoid delays in critical path activities so that it can shorten the project period by considering costs. This research used the PERT and CPM method approach in evaluating projects. This method begins with compiling a project network diagram and collecting information related to time variations that can occur on projects in the field. Some of the results of the processed data produced are information related to the critical path of the project, probability of project scheduling, and variations in operational costs according to the total duration of work. The data required in this research include the physical progress report of the project, Project Implementation Schedule, Curve S, and RAB.

Authors

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2024-09-30
DOI
https://doi.org/10.24843/jits.2024.v28.i02.p02
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

OPTIMIZING PROJECT SCHEDULING USING CPM AND PERT METHODS (CASE STUDY: PEJAMBON 8-STOREY FLAT, CENTRAL JAKARTA)

Anasya Arsita Laksmi, Dewi Fauzah, Rafiq Setyawan, Sigit Adi Soebakti
Jurnal Ilmiah Teknik Sipil
Management and Optimization Techniques
article

OPTIMIZING PROJECT SCHEDULING USING CPM AND PERT METHODS (CASE STUDY: PEJAMBON 8-STOREY FLAT, CENTRAL JAKARTA)

Anasya Arsita Laksmi, Dewi Fauzah, Rafiq Setyawan, Sigit Adi Soebakti
article en

Abstract

Pejambon 8 Storey-Flat Construction Project is one of the annual work programs through the allocation of Government Islamic Securities (SBSN) funding for the 2023 Ministry of Finance of the Republic of Indonesia. In this research, the CPM and PERT planning methods were used to implement project time management and increase effectiveness, by making schedules empirically. The aim of applying the CPM and PERT methods is to compare expectations with actual progress and avoid delays in critical path activities so that it can shorten the project period by considering costs. This research used the PERT and CPM method approach in evaluating projects. This method begins with compiling a project network diagram and collecting information related to time variations that can occur on projects in the field. Some of the results of the processed data produced are information related to the critical path of the project, probability of project scheduling, and variations in operational costs according to the total duration of work. The data required in this research include the physical progress report of the project, Project Implementation Schedule, Curve S, and RAB.

Jurnal Ilmiah Teknik SipilVol. 28(2)
Mercu Buana University (ID), Zen-Noh (Japan) (JP), Indonesia Defense University (ID)
Openalex Percentile: Top 47%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

OPTIMIZING PROJECT SCHEDULING USING CPM AND PERT METHODS (CASE STUDY: PEJAMBON 8-STOREY FLAT, CENTRAL JAKARTA) — Anasya Arsita Laksmi, Dewi Fauzah, et al. · Jurnal Ilmiah Teknik Sipil (2024) | TGRS Research Map | TGRS