Designing Project Overhead Cost Attribution Calculation Module to Enhance Capital Expenditure Control (Case Study: PT G)

Effective capital expenditure (capex) management in fixed asset investments, such as natural gas infrastructure projects, is essential to ensure investment feasibility. A component of capex is project overhead cost, which represent indirect expenses not directly linked to specific products or services and tend to increase as construction projects progress. This research addresses challenges faced by PT G, a national energy company, in allocating project overhead cost to ongoing projects using the SAP ERP system. The system only supports proportional cost allocation and lacks an integrated calculation method. Consequently, PT G relies on spreadsheets to manually calculate cost’s proportional allocations, based on project progress data from its project management information system (PMIS). This disconnected process results in redundancy, inadequate control over capital expenditure, and introduces risks such as human error, inconsistent results across users, and budget overruns. The aim of this study is to design an integrated construction overhead cost allocation module that utilizes real-time project progress data within PT G’s web-based project management system. The module is developed using the Object-Oriented Analysis and Design (OOAD) approach to ensure structured documentation and scalability. The findings show that the proposed module improves capex control by automating calculations, providing up-to-date information on realized spending and remaining budget limits, and enhancing data reliability and accountability through features such as activity logs and calculation logs. This integration reduces dependency on manual processes, streamlines workflows, and supports more accurate, transparent, and efficient financial management in infrastructure projects.

Authors

Institutions

Publication Details

Journal
E-Jurnal Akuntansi
Published
2025-08-20
DOI
https://doi.org/10.24843/eja.2025.v35.i07.p06
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Designing Project Overhead Cost Attribution Calculation Module to Enhance Capital Expenditure Control (Case Study: PT G)

Machmudin Eka Prasetya, Ide Dia Selly
E-Jurnal Akuntansi
Management and Optimization Techniques
article

Designing Project Overhead Cost Attribution Calculation Module to Enhance Capital Expenditure Control (Case Study: PT G)

Machmudin Eka Prasetya, Ide Dia Selly
article en

Abstract

Effective capital expenditure (capex) management in fixed asset investments, such as natural gas infrastructure projects, is essential to ensure investment feasibility. A component of capex is project overhead cost, which represent indirect expenses not directly linked to specific products or services and tend to increase as construction projects progress. This research addresses challenges faced by PT G, a national energy company, in allocating project overhead cost to ongoing projects using the SAP ERP system. The system only supports proportional cost allocation and lacks an integrated calculation method. Consequently, PT G relies on spreadsheets to manually calculate cost’s proportional allocations, based on project progress data from its project management information system (PMIS). This disconnected process results in redundancy, inadequate control over capital expenditure, and introduces risks such as human error, inconsistent results across users, and budget overruns. The aim of this study is to design an integrated construction overhead cost allocation module that utilizes real-time project progress data within PT G’s web-based project management system. The module is developed using the Object-Oriented Analysis and Design (OOAD) approach to ensure structured documentation and scalability. The findings show that the proposed module improves capex control by automating calculations, providing up-to-date information on realized spending and remaining budget limits, and enhancing data reliability and accountability through features such as activity logs and calculation logs. This integration reduces dependency on manual processes, streamlines workflows, and supports more accurate, transparent, and efficient financial management in infrastructure projects.

E-Jurnal AkuntansiVol. 35(7)
University of Indonesia (ID)
Openalex Percentile: Top 67%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Designing Project Overhead Cost Attribution Calculation Module to Enhance Capital Expenditure Control (Case Study: PT G) — Machmudin Eka Prasetya, Ide Dia Selly · E-Jurnal Akuntansi (2025) | TGRS Research Map | TGRS