In Belgium, geotechnical pile design is governed by ultimate capacity, and rarely involves the behaviour at service loads. On the other hand, a typical load test campaign focusses on the service settlement, and rarely reaches the ultimate capacity. This paper presents a case study for which this contrast between design and testing gave rise to a discrepancy in the measured settlements. A total of 5 static load tests and 124 dynamic load tests were performed on screw displacement, continuous flight auger (CFA), and bored piles. The measured settlement at service working loads ranged from 1 to 10 mm, despite a repetitive design made in relatively homogeneous ground conditions. Although all the piles satisfied the client settlement criteria, some piles did overperform. Therefore, there is room to improve the design in order to reduce, amongst other things, the environmental impact of the foundations.

Authors

Publication Details

Published
2025-05-01
DOI
https://doi.org/10.37308/dfieffc251540801
Primary Topic
Geotechnical Engineering and Soil Stabilization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Design Versus Load Testing: A Case Study on 124 Load Tests

Henri de Chaunac
Geotechnical Engineering and Soil Stabilization
article

Design Versus Load Testing: A Case Study on 124 Load Tests

Henri de Chaunac
article en

Abstract

In Belgium, geotechnical pile design is governed by ultimate capacity, and rarely involves the behaviour at service loads. On the other hand, a typical load test campaign focusses on the service settlement, and rarely reaches the ultimate capacity. This paper presents a case study for which this contrast between design and testing gave rise to a discrepancy in the measured settlements. A total of 5 static load tests and 124 dynamic load tests were performed on screw displacement, continuous flight auger (CFA), and bored piles. The measured settlement at service working loads ranged from 1 to 10 mm, despite a repetitive design made in relatively homogeneous ground conditions. Although all the piles satisfied the client settlement criteria, some piles did overperform. Therefore, there is room to improve the design in order to reduce, amongst other things, the environmental impact of the foundations.

Openalex Percentile: Top 77%
Geotechnical Engineering and Soil Stabilization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.