Coordination of Complex Geotechnical Works at a Tideway Site in Central London

The Thames Tideway Tunnel is one of the largest current infrastructure projects in the UK: upgrading London’s Victorian sewer network and extending over 25km across the city. The Tideway construction site at the Earl Pumping Station raised a number of technical, managerial, logistical and environmental challenges. At this 'postage stamp' sized site, a 52m deep drop shaft intercepting a 6.45m TBM-dug tunnel, a combined sewage overflow chamber and other ancillary structures have been constructed within heavily contaminated ground immediately adjacent to the live Thames Water pumping station serving the local South London community. Solutions developed between the joint venture of Costain, Vinci Grands Projects & Bachy Soletanche (CVBJV) and its partners, required extensive geotechnical works including: a diaphragm wall installed using a hydrofraise, Cased Continuous Flight Auger (CCFA), rotary bored and Sectional Flight Auger (SFA) piling, deep soil mixing (both panels and columns), and grouting (as jet, chemical and cementitious permeation). This paper discusses the approaches to reviewing the challenges, risks and lessons learnt on and off site, with the aim of showcasing the cohesive implementation and integration of complex schemes within the very congested site space and challenging delivery programme.

Authors

Publication Details

Published
2025-05-01
DOI
https://doi.org/10.37308/dfieffc25800401
Primary Topic
Tunneling and Rock Mechanics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Coordination of Complex Geotechnical Works at a Tideway Site in Central London

Adrian Liviu Bugea
Tunneling and Rock Mechanics
article

Coordination of Complex Geotechnical Works at a Tideway Site in Central London

Adrian Liviu Bugea
article en

Abstract

The Thames Tideway Tunnel is one of the largest current infrastructure projects in the UK: upgrading London’s Victorian sewer network and extending over 25km across the city. The Tideway construction site at the Earl Pumping Station raised a number of technical, managerial, logistical and environmental challenges. At this 'postage stamp' sized site, a 52m deep drop shaft intercepting a 6.45m TBM-dug tunnel, a combined sewage overflow chamber and other ancillary structures have been constructed within heavily contaminated ground immediately adjacent to the live Thames Water pumping station serving the local South London community. Solutions developed between the joint venture of Costain, Vinci Grands Projects & Bachy Soletanche (CVBJV) and its partners, required extensive geotechnical works including: a diaphragm wall installed using a hydrofraise, Cased Continuous Flight Auger (CCFA), rotary bored and Sectional Flight Auger (SFA) piling, deep soil mixing (both panels and columns), and grouting (as jet, chemical and cementitious permeation). This paper discusses the approaches to reviewing the challenges, risks and lessons learnt on and off site, with the aim of showcasing the cohesive implementation and integration of complex schemes within the very congested site space and challenging delivery programme.

Clean water and sanitation
Openalex Percentile: Top 77%
Tunneling and Rock Mechanics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Coordination of Complex Geotechnical Works at a Tideway Site in Central London — Adrian Liviu Bugea · (2025) | TGRS Research Map | TGRS