Deep Reinforcement Learning Scheduling Method for Prefabricated Bridge Construction

Off-site construction has become a widely accepted method due to its advantages in time-saving, rapid erection, and low cost. The rapid growth in this area demands better and more refined construction scheduling methods. Construction scheduling is complicated by the nature of various constraints in different aspects, such as resources and labour. Traditional methods, such as the Critical Path Method (CPM), lack consideration of various constraints, making them less applicable in real-world projects. This study proposes a Deep Reinforcement Learning (DRL) method to generate optimal construction schedules under limited labour and resource constraints. The objective of this study is to minimize the duration of construction projects. The proposed method introduces an improved DRL framework that enables the DRL to handle the scheduling of all construction processes. A case study is conducted on a real-world prefabricated bridge with 9 spans to evaluate the proposed method's performance. The DRL method is compared with traditional methods and the Genetic Algorithm (GA). The results show that DRL outperformed other methods in generating optimal construction schedules and required less running time. Therefore, the proposed method in this study extends the construction scheduling method and can be used in real projects.

Authors

Institutions

Publication Details

Published
2024-11-24
DOI
https://doi.org/10.71427/iccpmce2024/13
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Deep Reinforcement Learning Scheduling Method for Prefabricated Bridge Construction

Yuan Yao
BIM and Construction Integration
article

Deep Reinforcement Learning Scheduling Method for Prefabricated Bridge Construction

Yuan Yao
article en

Abstract

Off-site construction has become a widely accepted method due to its advantages in time-saving, rapid erection, and low cost. The rapid growth in this area demands better and more refined construction scheduling methods. Construction scheduling is complicated by the nature of various constraints in different aspects, such as resources and labour. Traditional methods, such as the Critical Path Method (CPM), lack consideration of various constraints, making them less applicable in real-world projects. This study proposes a Deep Reinforcement Learning (DRL) method to generate optimal construction schedules under limited labour and resource constraints. The objective of this study is to minimize the duration of construction projects. The proposed method introduces an improved DRL framework that enables the DRL to handle the scheduling of all construction processes. A case study is conducted on a real-world prefabricated bridge with 9 spans to evaluate the proposed method's performance. The DRL method is compared with traditional methods and the Genetic Algorithm (GA). The results show that DRL outperformed other methods in generating optimal construction schedules and required less running time. Therefore, the proposed method in this study extends the construction scheduling method and can be used in real projects.

Western Sydney University (AU)
Australian Government
Openalex Percentile: Top 68%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.