Construction scheduling challenges and implications: an interview study with industry professionals

Purpose The construction industry commonly experiences scheduling problems that lead to costly delays, rework, and other negative outcomes. While construction scheduling is a core subject in higher education, recent graduates often struggle to grasp the complexities of scheduling processes. This paper aims to identify specific construction processes that are most challenging for recent graduates and to explore the underlying factors contributing to these scheduling difficulties. Design/methodology/approach A qualitative research design was employed using semi-structured interviews with nineteen industry professionals, including general and specialty contractors. The interviews focused on identifying which construction processes recent graduates struggle with and the reasons behind these challenges. Findings The analysis revealed that tasks involving multiple trades are particularly difficult for new hires. Several factors were identified which included the difficulties in identifying mistakes, understanding the sequence of multi-trade processes, the unique and one-of-a-kind nature of many jobsite tasks and the need to reference numerous plan sheets to fully grasp a built element. Practical implications The findings highlight the critical need for exposure to complex, multi-trade tasks and emphasize the importance of learning through failure. To address this gap, the study recommends strengthening construction education through experiential learning methods such as simulations and hands-on activities that replicate real-world conditions and allow students to actively engage with the complexities of scheduling. Originality/value This study contributes to the research on construction scheduling education by identifying specific process-related challenges for new graduates and providing evidence-based recommendations to improve instructional practices. It offers valuable insights for educators and industry partners seeking to better prepare students for the demands of construction management.

Authors

Institutions

Publication Details

Journal
Higher Education Skills and Work-based Learning
Published
2025-08-22
DOI
https://doi.org/10.1108/heswbl-02-2025-0075
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Construction scheduling challenges and implications: an interview study with industry professionals

Steven K. Ayer, Andrew R. Kline
Higher Education Skills and Work-based Learning
Construction Project Management and Performance
article

Construction scheduling challenges and implications: an interview study with industry professionals

Steven K. Ayer, Andrew R. Kline
article en

Abstract

Purpose The construction industry commonly experiences scheduling problems that lead to costly delays, rework, and other negative outcomes. While construction scheduling is a core subject in higher education, recent graduates often struggle to grasp the complexities of scheduling processes. This paper aims to identify specific construction processes that are most challenging for recent graduates and to explore the underlying factors contributing to these scheduling difficulties. Design/methodology/approach A qualitative research design was employed using semi-structured interviews with nineteen industry professionals, including general and specialty contractors. The interviews focused on identifying which construction processes recent graduates struggle with and the reasons behind these challenges. Findings The analysis revealed that tasks involving multiple trades are particularly difficult for new hires. Several factors were identified which included the difficulties in identifying mistakes, understanding the sequence of multi-trade processes, the unique and one-of-a-kind nature of many jobsite tasks and the need to reference numerous plan sheets to fully grasp a built element. Practical implications The findings highlight the critical need for exposure to complex, multi-trade tasks and emphasize the importance of learning through failure. To address this gap, the study recommends strengthening construction education through experiential learning methods such as simulations and hands-on activities that replicate real-world conditions and allow students to actively engage with the complexities of scheduling. Originality/value This study contributes to the research on construction scheduling education by identifying specific process-related challenges for new graduates and providing evidence-based recommendations to improve instructional practices. It offers valuable insights for educators and industry partners seeking to better prepare students for the demands of construction management.

Higher Education Skills and Work-based LearningVol. 15(5)
California Polytechnic State University (US), University of Colorado Boulder (US), California State Polytechnic University (US)
Openalex Percentile: Top 74%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.