Abstract This paper presents Fitness-For-Service (FFS) studies from projects in which large as-laid gaps existed between flanges of pipeline and tie-in spool. The reasons for the large as-laid gaps are explained. The first case study is for a spool tie-in with water depth of about 140m. Incongruity of duration between operation turnaround and spool fabrication implied the need to perform the metrology in pipeline’s operating while tie-in in shutdown. A gap of 300mm was estimated and was considered in the finite element analysis (FEA) of the tie-in. The gap included margins for fabrication and metrology misalignments and pipeline contraction due to shutdown of the existing pipeline. An element removal and addition technique was used to simulate the initial gap and tie-in operation. The second case study is for a spool tie-in with water depth of about 50m. A gap of about 2.6m between the flanges of the pipeline and tie-in spool was found. Air bags were used to facilitate the tie-in. An automation tool was used to rebuild the surveyed spool shape after tie-in and the locked-in stress level was checked. Then all the functional loads were added to check the spool’s integrity. For both case studies, the spools’ integrities satisfied all the design criteria. This paper provides an insight into the analysis of spool tie-ins and considerable engineering reference significance. The work uses advanced automation tools to validate the design and installation methods. Lessons learned are also presented for future spool tie-in projects.

Authors

Institutions

Publication Details

Published
2025-06-22
DOI
https://doi.org/10.1115/omae2025-155520
Primary Topic
Engineering Structural Analysis Methods
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Fitness for Service Studies for Rigid Spool Tie-Ins

Xuexin Dai, Nicolas Henry, M. Faizal Chenoth T.
Engineering Structural Analysis Methods
article

Fitness for Service Studies for Rigid Spool Tie-Ins

Xuexin Dai, Nicolas Henry, M. Faizal Chenoth T.
article en

Abstract

Abstract This paper presents Fitness-For-Service (FFS) studies from projects in which large as-laid gaps existed between flanges of pipeline and tie-in spool. The reasons for the large as-laid gaps are explained. The first case study is for a spool tie-in with water depth of about 140m. Incongruity of duration between operation turnaround and spool fabrication implied the need to perform the metrology in pipeline’s operating while tie-in in shutdown. A gap of 300mm was estimated and was considered in the finite element analysis (FEA) of the tie-in. The gap included margins for fabrication and metrology misalignments and pipeline contraction due to shutdown of the existing pipeline. An element removal and addition technique was used to simulate the initial gap and tie-in operation. The second case study is for a spool tie-in with water depth of about 50m. A gap of about 2.6m between the flanges of the pipeline and tie-in spool was found. Air bags were used to facilitate the tie-in. An automation tool was used to rebuild the surveyed spool shape after tie-in and the locked-in stress level was checked. Then all the functional loads were added to check the spool’s integrity. For both case studies, the spools’ integrities satisfied all the design criteria. This paper provides an insight into the analysis of spool tie-ins and considerable engineering reference significance. The work uses advanced automation tools to validate the design and installation methods. Lessons learned are also presented for future spool tie-in projects.

Subsea 7 (France) (FR)
Openalex Percentile: Top 78%
Engineering Structural Analysis Methods
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.