“Analysis The Productivity Of Heavy Equipment Cut And Fill Work” (Case Study: Package 6th Leuwikeris Dam Project Tasikmalaya-Banjar)

This research examines the productivity of heavy equipment used in the Cut and Fill work at the Leuwikeris Dam Project in Tasikmalaya, Indonesia. The study highlights the importance of efficient resource utilization and the environmental and social impacts associated with dam construction. A time study method was employed to analyze productivity, focusing on various heavy equipment such as excavators, dump trucks, bulldozers, and vibratory rollers. The findings indicate that factors such as equipment breakdowns, weather conditions, and material supply delays significantly impact productivity. The results aim to inform civil engineering practices and improve the understanding of heavy construction equipment efficiency in development projects.

Authors

Institutions

Publication Details

Journal
Interdiciplinary Journal and Hummanity (INJURITY)
Published
2025-08-16
DOI
https://doi.org/10.58631/injurity.v4i8.1462
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

“Analysis The Productivity Of Heavy Equipment Cut And Fill Work” (Case Study: Package 6th Leuwikeris Dam Project Tasikmalaya-Banjar)

Nikko Rozy, Yanto Yanto, Cornelia Gina Fransisca, Muhamad Decky Pambudi
Interdiciplinary Journal and Hummanity (INJURITY)
Management and Optimization Techniques
article

“Analysis The Productivity Of Heavy Equipment Cut And Fill Work” (Case Study: Package 6th Leuwikeris Dam Project Tasikmalaya-Banjar)

Nikko Rozy, Yanto Yanto, Cornelia Gina Fransisca, Muhamad Decky Pambudi
article en

Abstract

This research examines the productivity of heavy equipment used in the Cut and Fill work at the Leuwikeris Dam Project in Tasikmalaya, Indonesia. The study highlights the importance of efficient resource utilization and the environmental and social impacts associated with dam construction. A time study method was employed to analyze productivity, focusing on various heavy equipment such as excavators, dump trucks, bulldozers, and vibratory rollers. The findings indicate that factors such as equipment breakdowns, weather conditions, and material supply delays significantly impact productivity. The results aim to inform civil engineering practices and improve the understanding of heavy construction equipment efficiency in development projects.

Interdiciplinary Journal and Hummanity (INJURITY)Vol. 4(8)
Universitas Swadaya Gunung Jati (ID)
Openalex Percentile: Top 68%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

“Analysis The Productivity Of Heavy Equipment Cut And Fill Work” (Case Study: Package 6th Leuwikeris Dam Project Tasikmalaya-Banjar) — Nikko Rozy, Yanto Yanto, et al. · Interdiciplinary Journal and Hummanity (INJURITY) (2025) | TGRS Research Map | TGRS