Earned Value Management Analysis of Construction Service Unit Price Contract: A Case Study at PT. XYZ

Achieving projects on time and within budget is critical for PT. XYZ to meet its work plan and production targets. The company undertakes massive, simultaneous development projects, requiring effective project management to prevent sharp production declines. Projects executed under unit-price Construction Service Contracts must be closely monitored in terms of scope, schedule, and cost. Moreover, these contracts entail long lead times (~6 months from tender to contractor mobilization), so early and accurate duration estimates are essential to avoid contractor unavailability. This study applied Earned Value Management (EVM) to integrate scope, time, and cost data for forecasting project completion. Three EVM-based schedule forecasting methods were compared: Planned Value (PV), Earned Duration (ED), and Earned Schedule (ES). Five well development projects (A–E) were analysed as case studies. The results show that PV and ED provided the most accurate duration forecasts. PV was consistently the top performer, with very low mean absolute percentage error (MAPE) for projects A, B, and C (0.3–1.2%). While PV’s accuracy dropped for the delayed projects D (35.5% error) and E (9.4%), its forecasts were still far more accurate than those from ES. The ED method was also reliable (MAPE < 12% for A–C) and showed a similar decline in accuracy for projects D and E.

Authors

Institutions

Publication Details

Journal
Journal Research of Social Science Economics and Management
Published
2025-08-18
DOI
https://doi.org/10.59141/jrssem.v5i1.985
Primary Topic
Value Engineering and Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Earned Value Management Analysis of Construction Service Unit Price Contract: A Case Study at PT. XYZ

I Putu Artama Wiguna, Disva Margaretha Prasetyo
Journal Research of Social Science Economics and Management
Value Engineering and Management
article

Earned Value Management Analysis of Construction Service Unit Price Contract: A Case Study at PT. XYZ

I Putu Artama Wiguna, Disva Margaretha Prasetyo
article en

Abstract

Achieving projects on time and within budget is critical for PT. XYZ to meet its work plan and production targets. The company undertakes massive, simultaneous development projects, requiring effective project management to prevent sharp production declines. Projects executed under unit-price Construction Service Contracts must be closely monitored in terms of scope, schedule, and cost. Moreover, these contracts entail long lead times (~6 months from tender to contractor mobilization), so early and accurate duration estimates are essential to avoid contractor unavailability. This study applied Earned Value Management (EVM) to integrate scope, time, and cost data for forecasting project completion. Three EVM-based schedule forecasting methods were compared: Planned Value (PV), Earned Duration (ED), and Earned Schedule (ES). Five well development projects (A–E) were analysed as case studies. The results show that PV and ED provided the most accurate duration forecasts. PV was consistently the top performer, with very low mean absolute percentage error (MAPE) for projects A, B, and C (0.3–1.2%). While PV’s accuracy dropped for the delayed projects D (35.5% error) and E (9.4%), its forecasts were still far more accurate than those from ES. The ED method was also reliable (MAPE < 12% for A–C) and showed a similar decline in accuracy for projects D and E.

Journal Research of Social Science Economics and ManagementVol. 5(1)
Sepuluh Nopember Institute of Technology (ID)
Openalex Percentile: Top 68%
Value Engineering and Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.