Spatial analysis and complexity evaluation for predicting rebar installation duration

Poor predictability of construction project duration and stagnant labor productivity highlight the need for scalable, data-driven monitoring solutions. This paper investigates how the relationship between activity complexity and duration can be quantified and leveraged. A grid-based spatial analysis is introduced to address this gap, combining BIM-derived complexity metrics for individual components (e.g., slabs) with CV-based as-performed activity classification, demonstrated in the context of rebar installation. The proposed activity classification model, ViTPoseActivity , achieves 97% accuracy in detecting on-site tasks using single-frame posture features. Correlation analysis on real-world construction data covering over 1,900 labor hours confirms a measurable positive relationship between activity complexity and duration. By combining as-designed and as-performed data in a spatial context, this paper provides a foundation for activity duration prediction, supporting proactive planning and future research in data-driven site management. • Grid-based spatial analysis quantifies activity complexity-duration relationships in construction. • CV-based activity classification architecture (ViTPoseActivity) achieves 97% detection accuracy. • BIM-derived complexity metrics enable localized correlation analysis for proactive planning. • Analysis of 1,900+ labor hours in rebar installation confirms measurable activity complexity-duration correlation.

Authors

Publication Details

Journal
Automation in Construction
Published
2025-08-20
DOI
https://doi.org/10.1016/j.autcon.2025.106462
Primary Topic
Infrastructure Maintenance and Monitoring
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Spatial analysis and complexity evaluation for predicting rebar installation duration

Fabian Pfitzner, André Borrmann, Alexander Braun, Frédéric Bosché
Automation in Construction
Infrastructure Maintenance and Monitoring
article

Spatial analysis and complexity evaluation for predicting rebar installation duration

Fabian Pfitzner, André Borrmann, Alexander Braun, Frédéric Bosché
article en

Abstract

Poor predictability of construction project duration and stagnant labor productivity highlight the need for scalable, data-driven monitoring solutions. This paper investigates how the relationship between activity complexity and duration can be quantified and leveraged. A grid-based spatial analysis is introduced to address this gap, combining BIM-derived complexity metrics for individual components (e.g., slabs) with CV-based as-performed activity classification, demonstrated in the context of rebar installation. The proposed activity classification model, ViTPoseActivity , achieves 97% accuracy in detecting on-site tasks using single-frame posture features. Correlation analysis on real-world construction data covering over 1,900 labor hours confirms a measurable positive relationship between activity complexity and duration. By combining as-designed and as-performed data in a spatial context, this paper provides a foundation for activity duration prediction, supporting proactive planning and future research in data-driven site management. • Grid-based spatial analysis quantifies activity complexity-duration relationships in construction. • CV-based activity classification architecture (ViTPoseActivity) achieves 97% detection accuracy. • BIM-derived complexity metrics enable localized correlation analysis for proactive planning. • Analysis of 1,900+ labor hours in rebar installation confirms measurable activity complexity-duration correlation.

Automation in ConstructionVol. 179
Climate action
Openalex Percentile: Top 77%
Infrastructure Maintenance and Monitoring
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Spatial analysis and complexity evaluation for predicting rebar installation duration — Fabian Pfitzner, André Borrmann, et al. · Automation in Construction (2025) | TGRS Research Map | TGRS