Analysis productivity and its impact on time and cost of implementation of the private residence project structure work
The construction project of Mrs. Tiya & Mr. Tom's Private Residence in Kemenuh-Gianyar is a 3-story villa development chosen as a case study due to discrepancies between the consultant's plans and the actual field conditions. This necessitated a method to optimize work completion. One proposed solution for accelerating the project was to add more workers. Based on the initial plan, the project required 104 days (3 months and 2 weeks) for completion, with a total structural work cost of Rp. 703,803,162.24. After analysis with the alternative of adding more workers, the project completion duration could return to the schedule of 90 days (3 months) or be accelerated by 12 days (2 weeks), with a total cost of Rp. 671,298,258.93. This concludes that adding more workers is an effective method to increase time efficiency by 14.29% and decrease costs by 4.6%, or the equivalent of Rp. 32,504,903.31.
Authors
- I Nyoman Ramia
- I Made Suardana Kader
- I Wayan Sudiasa
- Ida Bagus Bintana
- I Nengah Darma Susila
- I Made Budiadi
Institutions
- Jakarta State Polytechnic (ID)
Publication Details
- Journal
- International Research Journal of Engineering IT & Scientific Research
- Published
- 2025-08-07
- DOI
- https://doi.org/10.21744/irjeis.v11n5.2549
- Primary Topic
- Occupational Health and Safety Management
- Type
- article
- Field-Weighted Citation Impact
- 0.00