Analysis productivity and its impact on time and cost of implementation of the private residence project structure work

The construction project of Mrs. Tiya & Mr. Tom's Private Residence in Kemenuh-Gianyar is a 3-story villa development chosen as a case study due to discrepancies between the consultant's plans and the actual field conditions. This necessitated a method to optimize work completion. One proposed solution for accelerating the project was to add more workers. Based on the initial plan, the project required 104 days (3 months and 2 weeks) for completion, with a total structural work cost of Rp. 703,803,162.24. After analysis with the alternative of adding more workers, the project completion duration could return to the schedule of 90 days (3 months) or be accelerated by 12 days (2 weeks), with a total cost of Rp. 671,298,258.93. This concludes that adding more workers is an effective method to increase time efficiency by 14.29% and decrease costs by 4.6%, or the equivalent of Rp. 32,504,903.31.

Authors

Institutions

Publication Details

Journal
International Research Journal of Engineering IT & Scientific Research
Published
2025-08-07
DOI
https://doi.org/10.21744/irjeis.v11n5.2549
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis productivity and its impact on time and cost of implementation of the private residence project structure work

I Nyoman Ramia, I Made Suardana Kader, I Wayan Sudiasa, Ida Bagus Bintana et al.
International Research Journal of Engineering IT & Scientific Research
Occupational Health and Safety Management
article

Analysis productivity and its impact on time and cost of implementation of the private residence project structure work

I Nyoman Ramia, I Made Suardana Kader, I Wayan Sudiasa, Ida Bagus Bintana, I Nengah Darma Susila, I Made Budiadi
article en

Abstract

The construction project of Mrs. Tiya & Mr. Tom's Private Residence in Kemenuh-Gianyar is a 3-story villa development chosen as a case study due to discrepancies between the consultant's plans and the actual field conditions. This necessitated a method to optimize work completion. One proposed solution for accelerating the project was to add more workers. Based on the initial plan, the project required 104 days (3 months and 2 weeks) for completion, with a total structural work cost of Rp. 703,803,162.24. After analysis with the alternative of adding more workers, the project completion duration could return to the schedule of 90 days (3 months) or be accelerated by 12 days (2 weeks), with a total cost of Rp. 671,298,258.93. This concludes that adding more workers is an effective method to increase time efficiency by 14.29% and decrease costs by 4.6%, or the equivalent of Rp. 32,504,903.31.

International Research Journal of Engineering IT & Scientific ResearchVol. 11(5)
Jakarta State Polytechnic (ID)
Decent work and economic growth
Openalex Percentile: Top 69%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.