ANALISIS RASIO CHANGE ORDER PADA PROYEK KONSTRUKSI: STRATEGI PENGELOLAAN BIAYA KONTINGENSI

Change Orders (CO) represent a significant challenge in the construction industry, often leading to substantial adjustments in project budgets. COs, encompassing both scope additions and reductions, can result in discrepancies between initial budgets and final project costs, thus affecting project profitability and sustainability. To measure the impact of CO on budgets, this study employs the Change Order Ratio (COR) and its components: CORA (Change Order Ratio in Addition) for budget increases and CORS (Change Order Ratio in Subtraction) for budget reductions. This research analyzes data from 36 construction projects managed by PT XYZ in Indonesia from 2020 to 2024, with aims to (1) identify patterns in budget changes, (2) assess the statistical significance of CORA and CORS on COR, and (3) recommend contingency budgeting strategies. Findings reveal that both CORA and CORS have a significant impact on COR, with average values of 13.32% for CORA and 9.30% for CORS. Based on these findings, a contingency budget of 10-15% of the initial contract value is recommended. This study underscores the importance of effective CO management, particularly in anticipating scope additions, to maintain budget stability and enhance the accuracy of financial planning in construction projects.

Authors

Publication Details

Journal
Jurnal Infrastruktur
Published
2025-04-29
DOI
https://doi.org/10.35814/492f7h19
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS RASIO CHANGE ORDER PADA PROYEK KONSTRUKSI: STRATEGI PENGELOLAAN BIAYA KONTINGENSI

Mega Waty, Jatiaryo Sidiq Ramadhan
Jurnal Infrastruktur
Occupational Health and Safety Management
article

ANALISIS RASIO CHANGE ORDER PADA PROYEK KONSTRUKSI: STRATEGI PENGELOLAAN BIAYA KONTINGENSI

Mega Waty, Jatiaryo Sidiq Ramadhan
article en

Abstract

Change Orders (CO) represent a significant challenge in the construction industry, often leading to substantial adjustments in project budgets. COs, encompassing both scope additions and reductions, can result in discrepancies between initial budgets and final project costs, thus affecting project profitability and sustainability. To measure the impact of CO on budgets, this study employs the Change Order Ratio (COR) and its components: CORA (Change Order Ratio in Addition) for budget increases and CORS (Change Order Ratio in Subtraction) for budget reductions. This research analyzes data from 36 construction projects managed by PT XYZ in Indonesia from 2020 to 2024, with aims to (1) identify patterns in budget changes, (2) assess the statistical significance of CORA and CORS on COR, and (3) recommend contingency budgeting strategies. Findings reveal that both CORA and CORS have a significant impact on COR, with average values of 13.32% for CORA and 9.30% for CORS. Based on these findings, a contingency budget of 10-15% of the initial contract value is recommended. This study underscores the importance of effective CO management, particularly in anticipating scope additions, to maintain budget stability and enhance the accuracy of financial planning in construction projects.

Jurnal InfrastrukturVol. 11(1)
Industry, innovation and infrastructure
Openalex Percentile: Top 69%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.