Application of Risk Management Science in Construction Project Learning: Cost Contingency Study in Malang Raya Housing

Housing projects are classified as complex and therefore require risk management analysis for economic and business sustainability for developers. Objective: To apply the risk management science approach to understand the dynamics of contingency costs in real housing construction projects and relate it to strengthening student competencies in construction project-based learning. Method: This research is descriptive because it aims to provide an overview of the facts in the field and the observed phenomena regarding the analysis of dominant contingency cost factors in housing development projects in Malang Raya. Data analysis: Data was obtained through interviews and questionnaires, then analyzed on several factors that influence cost contingencies in housing projects. Results: The dominant factors influencing contingency costs in housing development projects in Malang Raya consist of four main factors: Design, financial, human resources, and engineering. The contingency costs in housing development projects in Malang Raya generally range from 5% to 7.5% of the total project value. Contingency costs are higher in type 36 and 45 housing projects, especially with DP below 20%. Solutions that can be implemented to address risks that cause contingency costs to arise include preventive and corrective actions tailored to each risk factor.

Authors

Institutions

Publication Details

Journal
Jurnal Penelitian Pendidikan IPA
Published
2025-07-25
DOI
https://doi.org/10.29303/jppipa.v11i7.11728
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Application of Risk Management Science in Construction Project Learning: Cost Contingency Study in Malang Raya Housing

Achfas Zacoeb, Retno Anggraini, Fairuz Firyal Qonitah
Jurnal Penelitian Pendidikan IPA
Occupational Health and Safety Management
article

Application of Risk Management Science in Construction Project Learning: Cost Contingency Study in Malang Raya Housing

Achfas Zacoeb, Retno Anggraini, Fairuz Firyal Qonitah
article en

Abstract

Housing projects are classified as complex and therefore require risk management analysis for economic and business sustainability for developers. Objective: To apply the risk management science approach to understand the dynamics of contingency costs in real housing construction projects and relate it to strengthening student competencies in construction project-based learning. Method: This research is descriptive because it aims to provide an overview of the facts in the field and the observed phenomena regarding the analysis of dominant contingency cost factors in housing development projects in Malang Raya. Data analysis: Data was obtained through interviews and questionnaires, then analyzed on several factors that influence cost contingencies in housing projects. Results: The dominant factors influencing contingency costs in housing development projects in Malang Raya consist of four main factors: Design, financial, human resources, and engineering. The contingency costs in housing development projects in Malang Raya generally range from 5% to 7.5% of the total project value. Contingency costs are higher in type 36 and 45 housing projects, especially with DP below 20%. Solutions that can be implemented to address risks that cause contingency costs to arise include preventive and corrective actions tailored to each risk factor.

Jurnal Penelitian Pendidikan IPAVol. 11(7)
University of Brawijaya (ID)
Openalex Percentile: Top 69%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.