SIMPLIFICATION AND OPTIMIZATION OF PROJECT STRUCTURES BASED ON PRECEDENCE-CONSTRAINED KNAPSACK PROBLEM

The COVID-19 pandemic has highlighted the structural vulnerability of construction projects, especially in crises when the effectiveness of traditional scheduling approaches has significantly decreased.This paper presents a novel algorithmic approach that combines graph-based project structure simplification with cost-constrained profit maximization based on the mathematical model of the precedenceconstrained knapsack problem.The method first reduces the size of the decision space by removing non-revenue-generating projects based on rules while preserving project logic dependencies and cost.After that, two optimization methodsinteger linear programming and graph theory heuristicsare used to select the project.Based on practical examples, simplification significantly reduces the need for computation, making it possible to find optimal solutions that were not manageable on the original structures.The algorithm prioritizes project paths that provide the highest specific gains while also meeting precedent requirements.The analysis confirmed the model's flexibility and applicability in different project environments.The presented approach thus contributes to the development of crisisresistant project management and, at the same time, offers a basis for the development of a generalizable decision support system.

Authors

Institutions

Publication Details

Published
2025-06-17
DOI
https://doi.org/10.22260/ccc2025/0015
Primary Topic
Software Engineering Techniques and Practices
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

SIMPLIFICATION AND OPTIMIZATION OF PROJECT STRUCTURES BASED ON PRECEDENCE-CONSTRAINED KNAPSACK PROBLEM

Gergely Lülök, Artúr Vlaszov, Sebestyén.Zoltán
Software Engineering Techniques and Practices
article

SIMPLIFICATION AND OPTIMIZATION OF PROJECT STRUCTURES BASED ON PRECEDENCE-CONSTRAINED KNAPSACK PROBLEM

Gergely Lülök, Artúr Vlaszov, Sebestyén.Zoltán
article en

Abstract

The COVID-19 pandemic has highlighted the structural vulnerability of construction projects, especially in crises when the effectiveness of traditional scheduling approaches has significantly decreased.This paper presents a novel algorithmic approach that combines graph-based project structure simplification with cost-constrained profit maximization based on the mathematical model of the precedenceconstrained knapsack problem.The method first reduces the size of the decision space by removing non-revenue-generating projects based on rules while preserving project logic dependencies and cost.After that, two optimization methodsinteger linear programming and graph theory heuristicsare used to select the project.Based on practical examples, simplification significantly reduces the need for computation, making it possible to find optimal solutions that were not manageable on the original structures.The algorithm prioritizes project paths that provide the highest specific gains while also meeting precedent requirements.The analysis confirmed the model's flexibility and applicability in different project environments.The presented approach thus contributes to the development of crisisresistant project management and, at the same time, offers a basis for the development of a generalizable decision support system.

Budapest University of Technology and Economics (HU)
Openalex Percentile: Top 69%
Software Engineering Techniques and Practices
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

SIMPLIFICATION AND OPTIMIZATION OF PROJECT STRUCTURES BASED ON PRECEDENCE-CONSTRAINED KNAPSACK PROBLEM — Gergely Lülök, Artúr Vlaszov, et al. · (2025) | TGRS Research Map | TGRS