Research on Selection of Electrical Equipment for Auxiliary Power Branch of Medium HPP

In view of the high amplitude and destructive nature of short-circuit current during short-circuiting of the auxiliary power branch of medium hydropower station, this paper analyzes in depth the characteristics of the auxiliary power branch of medium HPP under three-phase short-circuit fault conditions. Combined with the current power equipment production level, the measures to limit the three-phase shortcircuit current faults and the selection and calculation methods of electrical equipment when single-phase and three-phase equipment are used in the auxiliary power branch of medium HPP are studied in depth. The reliability of the calculation and selection methods of electrical equipment for auxiliary power branch circuits is verified through actual engineering cases. In this study, the practicality of design, safety of system operation and rationality of equipment selection are taken into account in the selection of electrical equipment for plant power.

Authors

Institutions

Publication Details

Published
2025-05-17
DOI
https://doi.org/10.1109/icet64964.2025.11103105
Primary Topic
Power Systems and Technologies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on Selection of Electrical Equipment for Auxiliary Power Branch of Medium HPP

Peng Yu, Yuhong Chen, Yi He, Dan Yu et al.
Power Systems and Technologies
article

Research on Selection of Electrical Equipment for Auxiliary Power Branch of Medium HPP

Peng Yu, Yuhong Chen, Yi He, Dan Yu, Ding Kuang
article en

Abstract

In view of the high amplitude and destructive nature of short-circuit current during short-circuiting of the auxiliary power branch of medium hydropower station, this paper analyzes in depth the characteristics of the auxiliary power branch of medium HPP under three-phase short-circuit fault conditions. Combined with the current power equipment production level, the measures to limit the three-phase shortcircuit current faults and the selection and calculation methods of electrical equipment when single-phase and three-phase equipment are used in the auxiliary power branch of medium HPP are studied in depth. The reliability of the calculation and selection methods of electrical equipment for auxiliary power branch circuits is verified through actual engineering cases. In this study, the practicality of design, safety of system operation and rationality of equipment selection are taken into account in the selection of electrical equipment for plant power.

Chengdu Medical College (CN)
Affordable and clean energy
Openalex Percentile: Top 81%
Power Systems and Technologies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Research on Selection of Electrical Equipment for Auxiliary Power Branch of Medium HPP — Peng Yu, Yuhong Chen, et al. · (2025) | TGRS Research Map | TGRS