Application of Earned Value Method for Analysing Cost and Time Performance in the Construction of the Bank Mandiri Flat in Pare-Pare, South Sulawesi

The Bank Mandiri Pare-Pare Sulawesi flat construction project is scheduled to be completed within 43 weeks with a contract value of Rp. 17,117,245,280. With time and cost constraints, good and thorough control is needed. The purpose of this study is to determine the cost and time performance at the end of the project completion. The method used in this study is the Earned Value method, which combines cost, time, and physical work performance elements. Data obtained from the project include the project schedule, Cost Estimate (RAB), weekly project reports, and actual costs. An analysis of costs, schedules, variances, and performance indices was conducted, highlighting issues that arose during the study. The Project Schedule Performance Index (SPI) at the 39th week review was 1.076, indicating that the project was ahead of schedule. The Project Cost Performance Index (CPI) from week 30 to week 38 showed values below 1, indicating that project expenditures exceeded the budget due to suboptimal progress weighting, as purchased materials were still in transit to the project site and had not yet been counted as progress by the owner. while in week 39, the index began to rise above 1 because progress weighting has become optimal, as the ordered goods have arrived and are now being accounted for in progress.

Authors

Publication Details

Journal
Jurnal Teknik dan Science
Published
2025-06-30
DOI
https://doi.org/10.56127/jts.v4i2.2230
Primary Topic
Value Engineering and Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Application of Earned Value Method for Analysing Cost and Time Performance in the Construction of the Bank Mandiri Flat in Pare-Pare, South Sulawesi

Victor Kurniawan, Agung Sakti Meldian, Ervina Yuliyanti
Jurnal Teknik dan Science
Value Engineering and Management
article

Application of Earned Value Method for Analysing Cost and Time Performance in the Construction of the Bank Mandiri Flat in Pare-Pare, South Sulawesi

Victor Kurniawan, Agung Sakti Meldian, Ervina Yuliyanti
article en

Abstract

The Bank Mandiri Pare-Pare Sulawesi flat construction project is scheduled to be completed within 43 weeks with a contract value of Rp. 17,117,245,280. With time and cost constraints, good and thorough control is needed. The purpose of this study is to determine the cost and time performance at the end of the project completion. The method used in this study is the Earned Value method, which combines cost, time, and physical work performance elements. Data obtained from the project include the project schedule, Cost Estimate (RAB), weekly project reports, and actual costs. An analysis of costs, schedules, variances, and performance indices was conducted, highlighting issues that arose during the study. The Project Schedule Performance Index (SPI) at the 39th week review was 1.076, indicating that the project was ahead of schedule. The Project Cost Performance Index (CPI) from week 30 to week 38 showed values below 1, indicating that project expenditures exceeded the budget due to suboptimal progress weighting, as purchased materials were still in transit to the project site and had not yet been counted as progress by the owner. while in week 39, the index began to rise above 1 because progress weighting has become optimal, as the ordered goods have arrived and are now being accounted for in progress.

Jurnal Teknik dan ScienceVol. 4(2)
Openalex Percentile: Top 69%
Value Engineering and Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.