Innovative Shoring Techniques for Deep Excavation in Downtown San Francisco

The Salesforce Tower is currently the tallest building on the west coast of United States, and the tower foundation construction involves the deepest excavation ever in downtown San Francisco. The foundation excavation utilized five shoring methods in three different construction stages: Cement deep soil mixing (CDSM) soldier pile shoring walls. A strut-wale shoring system with four levels bracing in the Phase I excavation, which allows the excavation down to 20-m below the street level. Twelve (12) reinforced jet grout shafts as excavation shoring extending from the bottom of the Phase I excavation. A 41-m diameter secant pile ring as excavation shoring in Phase II excavation, which extends down from the bottom of the Phase I excavation and provides shoring for excavation to 29-m down from the street level. A three-level tieback system allows excavation in the Plaza area in Phase III of the project. The presentation focuses on the use of innovative shoring techniques in combination with the conventional shoring method to meet significant challenges in the excavation, including very tight shoring deflection limits in the dense urban area, risk of base heaving due to artesian pressures, risk of differential settlement in adjacent building due to the excavation, design of a new shoring system within a braced shoring that were already in place, interfacing with adjacent shoring system and construction at Transbay Transit Center, innovative uses of jet grouting and secant piles as shoring methods in complex soil conditions, and complex construction logistics with multiple construction trades interfacing with shoring and excavation.  The innovative shoring design allows the complex and demanding deep excavation project to be successfully completed without a hitch.

Authors

Publication Details

Published
2025-05-01
DOI
https://doi.org/10.37308/dfieffc251190414
Primary Topic
Geotechnical Engineering and Underground Structures
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Innovative Shoring Techniques for Deep Excavation in Downtown San Francisco

Suwei Yao
Geotechnical Engineering and Underground Structures
article

Innovative Shoring Techniques for Deep Excavation in Downtown San Francisco

Suwei Yao
article en

Abstract

The Salesforce Tower is currently the tallest building on the west coast of United States, and the tower foundation construction involves the deepest excavation ever in downtown San Francisco. The foundation excavation utilized five shoring methods in three different construction stages: Cement deep soil mixing (CDSM) soldier pile shoring walls. A strut-wale shoring system with four levels bracing in the Phase I excavation, which allows the excavation down to 20-m below the street level. Twelve (12) reinforced jet grout shafts as excavation shoring extending from the bottom of the Phase I excavation. A 41-m diameter secant pile ring as excavation shoring in Phase II excavation, which extends down from the bottom of the Phase I excavation and provides shoring for excavation to 29-m down from the street level. A three-level tieback system allows excavation in the Plaza area in Phase III of the project. The presentation focuses on the use of innovative shoring techniques in combination with the conventional shoring method to meet significant challenges in the excavation, including very tight shoring deflection limits in the dense urban area, risk of base heaving due to artesian pressures, risk of differential settlement in adjacent building due to the excavation, design of a new shoring system within a braced shoring that were already in place, interfacing with adjacent shoring system and construction at Transbay Transit Center, innovative uses of jet grouting and secant piles as shoring methods in complex soil conditions, and complex construction logistics with multiple construction trades interfacing with shoring and excavation.  The innovative shoring design allows the complex and demanding deep excavation project to be successfully completed without a hitch.

Openalex Percentile: Top 79%
Geotechnical Engineering and Underground Structures
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Innovative Shoring Techniques for Deep Excavation in Downtown San Francisco — Suwei Yao · (2025) | TGRS Research Map | TGRS