Analysis of The Influence of Change Contract Order, Labor, Materials and Tools on the Performance of the Implementation Time Low-Rise State Building Project

Construction of state low-rise buildings in Pangkalpinang city is a common project that usually built by The Public Works Department of Pangkalpinang. The problem often faced by construction of state low-rise buildings projects at Pangkalpinang is the low performance of time (Delay). This condition be expected caused by Change Contract Order (CCO), man power, materials, and machine, This research aims to analyze the influence of those factors on delay time in state low-rise building construction projects. The analysis used in this research is multiple regression with SPSS. This research finds that both and parsially the 4 (four) factors influence the time-performance (delay) of low-rise state building construction. Based on data analysis, the equation Y = 3.887 + 0.390 X1 + 0.278 X2 + 0.265 X3 + 0.341 X4. Based on the results of the Coefficient of Determination Test, simultaneously CCO Factors (X1), Manpower Factors (X2), Materials Factors (X3) and Machines Factors (X4) have an influence contribution of 74.0 % of Time Performance (Y). Meanwhile, for the results of the most dominant factor analysis using Beta Standardized x Zero-Order, it was found that the CCO Factor (X2) was the most dominant factor that could influence time performance with an influence value of 23.99%. Considerations in determining alternative solutions to control time performance in state low-rise building construction projects are carried out on the most dominant factor, namely the CCO Factor (X1).

Authors

Institutions

Publication Details

Journal
Eduvest - Journal Of Universal Studies
Published
2025-08-08
DOI
https://doi.org/10.59188/eduvest.v5i8.50876
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of The Influence of Change Contract Order, Labor, Materials and Tools on the Performance of the Implementation Time Low-Rise State Building Project

Pahala R. Tobing
Eduvest - Journal Of Universal Studies
Management and Optimization Techniques
article

Analysis of The Influence of Change Contract Order, Labor, Materials and Tools on the Performance of the Implementation Time Low-Rise State Building Project

Pahala R. Tobing
article en

Abstract

Construction of state low-rise buildings in Pangkalpinang city is a common project that usually built by The Public Works Department of Pangkalpinang. The problem often faced by construction of state low-rise buildings projects at Pangkalpinang is the low performance of time (Delay). This condition be expected caused by Change Contract Order (CCO), man power, materials, and machine, This research aims to analyze the influence of those factors on delay time in state low-rise building construction projects. The analysis used in this research is multiple regression with SPSS. This research finds that both and parsially the 4 (four) factors influence the time-performance (delay) of low-rise state building construction. Based on data analysis, the equation Y = 3.887 + 0.390 X1 + 0.278 X2 + 0.265 X3 + 0.341 X4. Based on the results of the Coefficient of Determination Test, simultaneously CCO Factors (X1), Manpower Factors (X2), Materials Factors (X3) and Machines Factors (X4) have an influence contribution of 74.0 % of Time Performance (Y). Meanwhile, for the results of the most dominant factor analysis using Beta Standardized x Zero-Order, it was found that the CCO Factor (X2) was the most dominant factor that could influence time performance with an influence value of 23.99%. Considerations in determining alternative solutions to control time performance in state low-rise building construction projects are carried out on the most dominant factor, namely the CCO Factor (X1).

Eduvest - Journal Of Universal StudiesVol. 5(8)
Mercu Buana University (ID)
Openalex Percentile: Top 70%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis of The Influence of Change Contract Order, Labor, Materials and Tools on the Performance of the Implementation Time Low-Rise State Building Project — Pahala R. Tobing · Eduvest - Journal Of Universal Studies (2025) | TGRS Research Map | TGRS