ENHANCING LABOR PRODUCTIVITY TO MITIGATE TIME AND COST OVERRUNS IN CONSTRUCTION PROJECTS

Time and cost overruns present difficulties in construction projects, particularly in emerging nations where worker performance inefficiencies substantially impede project accomplishment. This research examines the influence of worker productivity on project performance, emphasizing its significance in reducing delays and budget overruns. Fifty labor productivity parameters were found after a comprehensive literature analysis and confirmed through expert consultation. These aspects include several areas, such as labor skills, training, quality of supervision, communication, the working environment, availability of resources, equipment efficiency, site management, and safety measures. A mixed-methods research approach was used to guarantee comprehensive and in-depth examination. Quantitative data were gathered using standardized questionnaires disseminated among project managers, site engineers, and contractors across 20 infrastructure projects in Iraq. The relative importance index (RII) was used to prioritize the relevance of each element. Additionally, regression analysis was used to investigate the correlation between labor productivity and time-cost performance metrics. Concurrently, qualitative insights were obtained via semi structured interviews with industry experts to enhance the understanding of the quantitative results. The findings indicate that the primary factors enhancing worker productivity include skill level RII (0.88), training and development (0.85), effective supervision (0.83), and material delivery timeliness (0.82). The results demonstrate a significant association between labor efficiency and decreases in time (R² = 0.67) and cost overruns (R² = 0.61). The study concludes with actionable suggestions for project stakeholders to effectively manage workforce-related factors and improve overall project delivery results.

Authors

Institutions

Publication Details

Journal
International Journal of Environmental Research and Earth Science
Published
2025-08-08
DOI
https://doi.org/10.70382/caijeres.v8i4.031
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ENHANCING LABOR PRODUCTIVITY TO MITIGATE TIME AND COST OVERRUNS IN CONSTRUCTION PROJECTS

ali hussien
International Journal of Environmental Research and Earth Science
Construction Project Management and Performance
article

ENHANCING LABOR PRODUCTIVITY TO MITIGATE TIME AND COST OVERRUNS IN CONSTRUCTION PROJECTS

ali hussien
article en

Abstract

Time and cost overruns present difficulties in construction projects, particularly in emerging nations where worker performance inefficiencies substantially impede project accomplishment. This research examines the influence of worker productivity on project performance, emphasizing its significance in reducing delays and budget overruns. Fifty labor productivity parameters were found after a comprehensive literature analysis and confirmed through expert consultation. These aspects include several areas, such as labor skills, training, quality of supervision, communication, the working environment, availability of resources, equipment efficiency, site management, and safety measures. A mixed-methods research approach was used to guarantee comprehensive and in-depth examination. Quantitative data were gathered using standardized questionnaires disseminated among project managers, site engineers, and contractors across 20 infrastructure projects in Iraq. The relative importance index (RII) was used to prioritize the relevance of each element. Additionally, regression analysis was used to investigate the correlation between labor productivity and time-cost performance metrics. Concurrently, qualitative insights were obtained via semi structured interviews with industry experts to enhance the understanding of the quantitative results. The findings indicate that the primary factors enhancing worker productivity include skill level RII (0.88), training and development (0.85), effective supervision (0.83), and material delivery timeliness (0.82). The results demonstrate a significant association between labor efficiency and decreases in time (R² = 0.67) and cost overruns (R² = 0.61). The study concludes with actionable suggestions for project stakeholders to effectively manage workforce-related factors and improve overall project delivery results.

International Journal of Environmental Research and Earth Science
Universiti Putra Malaysia (MY)
Decent work and economic growth
Openalex Percentile: Top 76%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.