Project control using S Curve in provision of pedestal crane at PT. Medco E&P Natuna - West Belut Platform

In the implementation of a project, three main aspects are indicators of the success of the project: cost, schedule, and quality. If the cost and time of project implementation are in accordance with the planning and quality requirements, then the project can be said to be successful. Time plays a significant role in construction management projects, where time is also a management function. With good and proper time control, obstacles to delays in project implementation can be avoided as much as possible. The purpose of this study was to determine the cause of the achievement or deviation of work between the realization in the field and the planned time schedule for the procurement of a pedestal crane unit for a new platform in the operational area of ​​ block-B-Natuna.

Authors

Publication Details

Journal
Priviet Social Sciences Journal
Published
2025-08-11
DOI
https://doi.org/10.55942/pssj.v5i8.489
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Project control using S Curve in provision of pedestal crane at PT. Medco E&P Natuna - West Belut Platform

Khalid Munawar, Rahmat Rahmat, Marhaendra Natawibawa, Jefri Imron et al.
Priviet Social Sciences Journal
Occupational Health and Safety Management
article

Project control using S Curve in provision of pedestal crane at PT. Medco E&P Natuna - West Belut Platform

Khalid Munawar, Rahmat Rahmat, Marhaendra Natawibawa, Jefri Imron, Dean Anggara Putra, Rifo Nurlaksana Restu, Hery Sumardiyanto, Thomas Junaedi
article en

Abstract

In the implementation of a project, three main aspects are indicators of the success of the project: cost, schedule, and quality. If the cost and time of project implementation are in accordance with the planning and quality requirements, then the project can be said to be successful. Time plays a significant role in construction management projects, where time is also a management function. With good and proper time control, obstacles to delays in project implementation can be avoided as much as possible. The purpose of this study was to determine the cause of the achievement or deviation of work between the realization in the field and the planned time schedule for the procurement of a pedestal crane unit for a new platform in the operational area of ​​ block-B-Natuna.

Priviet Social Sciences JournalVol. 5(8)
Industry, innovation and infrastructure
Openalex Percentile: Top 70%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.