Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction

The cable crane is the core hoisting equipment for high arch dam construction, and its hoisting trajectory is critical for both operational efficiency and safety. However, current trajectory planning does not adequately consider the underactuated characteristics of the cable crane. For instance, sudden stops or abrupt changes in direction can easily induce large swings of the bucket, causing safety risks and equipment wear. To address this issue, this paper developed a trajectory planning model for obstacle avoidance with smooth transitions in cable crane hoisting for arch dams and solved the high-dimensional optimization problem using a path–velocity decoupling strategy. First, a shortest path with geometrical conciseness and free collision was generated based on an improved A* algorithm to reduce the frequency of directional changes. Next, for different hoisting scenarios, segmented S-curve and polynomial velocity functions were proposed to ensure smooth velocity transitions. Then, an orthogonal experimental design was employed to generate a cluster of candidate trajectories that meet kinematic constraints, from which the optimal trajectory was selected using a multi-objective evaluation function. The results demonstrate that the motion trajectory planned using the proposed method is notably smoother. Compared with the traditional trapezoidal velocity method, it reduces the maximum swing amplitude of the bucket by 40.78% at a modest time cost. In real-time obstacle avoidance scenarios, the approach outperforms emergency-stop strategies, reducing the bucket’s maximum swing amplitude by 30.48%. This work will provide a reference for engineers to optimize the trajectory of large lifting equipment in construction fields such as high arch dams and bridges.

Authors

Institutions

Publication Details

Journal
Applied Sciences
Published
2025-08-12
DOI
https://doi.org/10.3390/app15168894
Citations
1
Primary Topic
Tunneling and Rock Mechanics
Type
article
Field-Weighted Citation Impact
0.95

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction

Yihong Zhou, Chunju Zhao, Hongsheng Xu, Fang Wang et al.
1 citations
Applied Sciences
Tunneling and Rock Mechanics
0.95
article

Smooth Obstacle-Avoidance Trajectory Planning for Cable Cranes During Concrete Hoisting in Arch Dam Construction

Yihong Zhou, Chunju Zhao, Hongsheng Xu, Fang Wang, Z. Liang, Lei Lei, Huawei Zhou
article en
1 citations

Abstract

The cable crane is the core hoisting equipment for high arch dam construction, and its hoisting trajectory is critical for both operational efficiency and safety. However, current trajectory planning does not adequately consider the underactuated characteristics of the cable crane. For instance, sudden stops or abrupt changes in direction can easily induce large swings of the bucket, causing safety risks and equipment wear. To address this issue, this paper developed a trajectory planning model for obstacle avoidance with smooth transitions in cable crane hoisting for arch dams and solved the high-dimensional optimization problem using a path–velocity decoupling strategy. First, a shortest path with geometrical conciseness and free collision was generated based on an improved A* algorithm to reduce the frequency of directional changes. Next, for different hoisting scenarios, segmented S-curve and polynomial velocity functions were proposed to ensure smooth velocity transitions. Then, an orthogonal experimental design was employed to generate a cluster of candidate trajectories that meet kinematic constraints, from which the optimal trajectory was selected using a multi-objective evaluation function. The results demonstrate that the motion trajectory planned using the proposed method is notably smoother. Compared with the traditional trapezoidal velocity method, it reduces the maximum swing amplitude of the bucket by 40.78% at a modest time cost. In real-time obstacle avoidance scenarios, the approach outperforms emergency-stop strategies, reducing the bucket’s maximum swing amplitude by 30.48%. This work will provide a reference for engineers to optimize the trajectory of large lifting equipment in construction fields such as high arch dams and bridges.

Applied SciencesVol. 15(16)
Hubei University of Technology (CN)
Hubei University of Technology
Openalex Percentile: Top 23%
Tunneling and Rock Mechanics
0.95
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.