The structural equation model of risk factors influencing government irrigation project

Abstract This research aimed to study the impact of risk factors on the success of irrigation projects in Thailand. Data were collected using questionnaires at irrigation agencies in various projects. A structural equation model (SEM) was then developed, and the risks of various factors affecting the irrigation project were analysed. The study results found that the risk factors affecting the construction process were as follows: The study results found that the risk factors affecting the construction process were as follows: In terms of work control, the presence of multiple chains of command led to delays in decision-making. This was followed by delays caused by the employer’s material approval process, the lack of clear and detailed construction project planning by the employer, and delays resulting from the performance of subcontractors. The factors mentioned above resulted in the highest score of all 56 factors. The findings of this study showed factors that affected the project, causing project managers, related agencies, or stakeholders to know and find a way for problem solution. The results of this study have found that the SEM values of risk management affecting the construction irrigation project have passed the criteria and have caused the relationship. Those values consist of significance chi-square ( p -value = 0.799), chi-square relation value at 0.413, normal fit index (NFI) value at 0.999, goodness of fit index (GFI) value at 0.999, CFI value at 0.999, standardised root mean square residual (RMR) value at 0.029, and root mean square error of approximation (RMSEA) value at 0.001.

Authors

Institutions

Publication Details

Journal
Organization Technology and Management in Construction An International Journal
Published
2025-01-01
DOI
https://doi.org/10.2478/otmcj-2025-0010
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The structural equation model of risk factors influencing government irrigation project

Anuchat Leeanansaksiri, Phongphan Tankasem, Wuttipong Kusonkhum
Organization Technology and Management in Construction An International Journal
Construction Project Management and Performance
article

The structural equation model of risk factors influencing government irrigation project

Anuchat Leeanansaksiri, Phongphan Tankasem, Wuttipong Kusonkhum
article en

Abstract

Abstract This research aimed to study the impact of risk factors on the success of irrigation projects in Thailand. Data were collected using questionnaires at irrigation agencies in various projects. A structural equation model (SEM) was then developed, and the risks of various factors affecting the irrigation project were analysed. The study results found that the risk factors affecting the construction process were as follows: The study results found that the risk factors affecting the construction process were as follows: In terms of work control, the presence of multiple chains of command led to delays in decision-making. This was followed by delays caused by the employer’s material approval process, the lack of clear and detailed construction project planning by the employer, and delays resulting from the performance of subcontractors. The factors mentioned above resulted in the highest score of all 56 factors. The findings of this study showed factors that affected the project, causing project managers, related agencies, or stakeholders to know and find a way for problem solution. The results of this study have found that the SEM values of risk management affecting the construction irrigation project have passed the criteria and have caused the relationship. Those values consist of significance chi-square ( p -value = 0.799), chi-square relation value at 0.413, normal fit index (NFI) value at 0.999, goodness of fit index (GFI) value at 0.999, CFI value at 0.999, standardised root mean square residual (RMR) value at 0.029, and root mean square error of approximation (RMSEA) value at 0.001.

Organization Technology and Management in Construction An International JournalVol. 17(1)
Mahasarakham University (TH), Khon Kaen University (TH), North Eastern University (TH)
Openalex Percentile: Top 76%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.