Optimal Design of the Cable Layout in a Wind Farm Using Modified Prime Algorithm

The optimization of cable routing in mediumvoltage networks is a crucial factor in improving the efficiency and cost-effectiveness of wind farm development. This paper proposes a modified Prim's Algorithm that incorporates topographical constraints and introduces intermediate splice nodes to optimize cable layout between wind turbines and substations. Using a graph-based approach, the algorithm avoids restricted areas and calculates the shortest feasible cable routes. Simulations conducted under various wind turbine configurations show that the modified algorithm reduces total cable length and improves network connectivity compared to conventional methods. The results highlight the potential of the proposed method for enhancing energy distribution efficiency and reliability in renewable energy systems. This approach is adaptable to other renewable infrastructures such as solar power networks and microgrids, supporting global efforts toward sustainable energy solutions

Authors

Institutions

Publication Details

Published
2025-06-12
DOI
https://doi.org/10.1109/icera66156.2025.11087267
Primary Topic
Advanced Manufacturing and Logistics Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimal Design of the Cable Layout in a Wind Farm Using Modified Prime Algorithm

Indra Dwi Suryanto, Roni Irnawan, Lesnanto Multa Putranto, M. Isnaeni Bambang Setyonegoro
1 links
Advanced Manufacturing and Logistics Optimization
article

Optimal Design of the Cable Layout in a Wind Farm Using Modified Prime Algorithm

Indra Dwi Suryanto, Roni Irnawan, Lesnanto Multa Putranto, M. Isnaeni Bambang Setyonegoro
article en

Abstract

The optimization of cable routing in mediumvoltage networks is a crucial factor in improving the efficiency and cost-effectiveness of wind farm development. This paper proposes a modified Prim's Algorithm that incorporates topographical constraints and introduces intermediate splice nodes to optimize cable layout between wind turbines and substations. Using a graph-based approach, the algorithm avoids restricted areas and calculates the shortest feasible cable routes. Simulations conducted under various wind turbine configurations show that the modified algorithm reduces total cable length and improves network connectivity compared to conventional methods. The results highlight the potential of the proposed method for enhancing energy distribution efficiency and reliability in renewable energy systems. This approach is adaptable to other renewable infrastructures such as solar power networks and microgrids, supporting global efforts toward sustainable energy solutions

Universitas Gadjah Mada (ID)
Affordable and clean energy
Openalex Percentile: Top 72%
Advanced Manufacturing and Logistics Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Optimal Design of the Cable Layout in a Wind Farm Using Modified Prime Algorithm — Indra Dwi Suryanto, Roni Irnawan, et al. · (2025) | TGRS Research Map | TGRS