Continuous Plugging and Abandonment of Drilled Open Holes Using Multi-Stage Balanced Cement Plugs on a Research Test Rig

ABSTRACT: The unique practice for the drilling test facility is to place a group of multi-stage balanced cement plugs in one run by pulling the cement string to the top of the previous plug and pumping the next plug until all the planned plugs are finished. More than 65 plug jobs have been completed over the past 10 years of drilling operations, mostly in deviated or horizontal wellbores through two major parent wells. No well control events have ever been encountered during the past drilling and testing operations. No losses or flowing occurred during any plug jobs. The goal of this paper is to share multiple cement plug operational practices and successes which aim to ensure successful kick-off of open holes below the casing shoe, retain earth integrity to not interfere with any future downhole drilling testing, and maintain a healthy test well that can be reused for many years to come.

Authors

Institutions

Publication Details

Published
2025-06-08
DOI
https://doi.org/10.56952/arma-2025-0112
Primary Topic
Drilling and Well Engineering
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Continuous Plugging and Abandonment of Drilled Open Holes Using Multi-Stage Balanced Cement Plugs on a Research Test Rig

C. Wright, G. Stuart, G. Chen, Peng Wang
Drilling and Well Engineering
article

Continuous Plugging and Abandonment of Drilled Open Holes Using Multi-Stage Balanced Cement Plugs on a Research Test Rig

C. Wright, G. Stuart, G. Chen, Peng Wang
article en

Abstract

ABSTRACT: The unique practice for the drilling test facility is to place a group of multi-stage balanced cement plugs in one run by pulling the cement string to the top of the previous plug and pumping the next plug until all the planned plugs are finished. More than 65 plug jobs have been completed over the past 10 years of drilling operations, mostly in deviated or horizontal wellbores through two major parent wells. No well control events have ever been encountered during the past drilling and testing operations. No losses or flowing occurred during any plug jobs. The goal of this paper is to share multiple cement plug operational practices and successes which aim to ensure successful kick-off of open holes below the casing shoe, retain earth integrity to not interfere with any future downhole drilling testing, and maintain a healthy test well that can be reused for many years to come.

GTx (United States) (US), National Oilwell Varco (United States) (US)
Openalex Percentile: Top 76%
Drilling and Well Engineering
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Continuous Plugging and Abandonment of Drilled Open Holes Using Multi-Stage Balanced Cement Plugs on a Research Test Rig — C. Wright, G. Stuart, et al. · (2025) | TGRS Research Map | TGRS