Slope monitoring plan and risk management process- Case study: Chadormalu open pit mine

ABSTRACT: A comprehensive understanding of the risks and the implementation of suitable control operations are crucial for the effective management of unstable walls in large open pit mines. The Chadormalu mine is divided into five domains. Domain 1 is of paramount importance, as reducing the slope is not a viable option. The wall is situated on a substantial portion of the ore, in conjunction with structures and power towers. The analysis, which attributes the properties of the tectonized zone to the unstable regions, yields results that closely align with the actual conditions. Consequently, the implementation of the TARP program and monitoring system effectively addressed the instability. This strategy facilitated mitigation with minimal associated costs and risks. Nevertheless, the potential loss of 2 million tons of waste remains a concern. To address this, a numerical analysis of the finite element was conducted, focusing exclusively on the primary structures, according to the Moher-Columb criterion. A comprehensive examination of the area revealed wedge-shaped collapses, as well as plane ruptures and block toppling failure.

Authors

Institutions

Publication Details

Published
2025-06-08
DOI
https://doi.org/10.56952/arma-2025-0173
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Slope monitoring plan and risk management process- Case study: Chadormalu open pit mine

Yousef Abolfazlzadeh, Soroush Ali Madadi, Saeed Mahmoudi Janaki, Abolfazl Rezaeipour
Mining Techniques and Economics
article

Slope monitoring plan and risk management process- Case study: Chadormalu open pit mine

Yousef Abolfazlzadeh, Soroush Ali Madadi, Saeed Mahmoudi Janaki, Abolfazl Rezaeipour
article en

Abstract

ABSTRACT: A comprehensive understanding of the risks and the implementation of suitable control operations are crucial for the effective management of unstable walls in large open pit mines. The Chadormalu mine is divided into five domains. Domain 1 is of paramount importance, as reducing the slope is not a viable option. The wall is situated on a substantial portion of the ore, in conjunction with structures and power towers. The analysis, which attributes the properties of the tectonized zone to the unstable regions, yields results that closely align with the actual conditions. Consequently, the implementation of the TARP program and monitoring system effectively addressed the instability. This strategy facilitated mitigation with minimal associated costs and risks. Nevertheless, the potential loss of 2 million tons of waste remains a concern. To address this, a numerical analysis of the finite element was conducted, focusing exclusively on the primary structures, according to the Moher-Columb criterion. A comprehensive examination of the area revealed wedge-shaped collapses, as well as plane ruptures and block toppling failure.

British Columbia Centre on Substance Use (CA), Iron Ore Company (Canada) (CA)
Openalex Percentile: Top 77%
Mining Techniques and Economics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Slope monitoring plan and risk management process- Case study: Chadormalu open pit mine — Yousef Abolfazlzadeh, Soroush Ali Madadi, et al. · (2025) | TGRS Research Map | TGRS