Analisa Penambahan Jam Lembur Kerja dengan Metode Crash Program pada Proyek Pembangunan Terminal Tipe B Gorontalo

Delays in project execution can be addressed through project control techniques such as the crash method, which aims to accelerate project duration without significantly increasing costs. This study investigates the application of the crash method in the acceleration of a Type B Terminal construction project (Phase 1) to evaluate its impact on project duration and cost. The research employs a quantitative descriptive approach, combining literature review and field observation. Data collection includes the original project schedule and cost information, followed by critical path analysis using the Critical Path Method (CPM). Based on the identified critical activities, the study applies crash analysis by reducing the duration of critical tasks and adding overtime hours, then compares various scenarios to determine the most cost-effective acceleration strategy. The results reveal that an additional 4 hours of overtime is the most efficient option, reducing the project duration by 43% while incurring the lowest total cost of Rp 3,860,600,576.59. This finding highlights that proper application of the crash method can lead to substantial time savings with manageable cost implications. In conclusion, the crash method proves to be an effective strategy for project time optimization when supported by accurate scheduling, cost analysis, and critical activity identification. The study recommends further research to validate these findings across different types of infrastructure projects using updated specifications.

Authors

Institutions

Publication Details

Journal
Research Review Jurnal Ilmiah Multidisiplin
Published
2025-07-25
DOI
https://doi.org/10.54923/researchreview.v4i1.208
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisa Penambahan Jam Lembur Kerja dengan Metode Crash Program pada Proyek Pembangunan Terminal Tipe B Gorontalo

Moh. Yusuf Tuloli, Arfan Utiarahman, Tandimas Febriyanto
Research Review Jurnal Ilmiah Multidisiplin
Management and Optimization Techniques
article

Analisa Penambahan Jam Lembur Kerja dengan Metode Crash Program pada Proyek Pembangunan Terminal Tipe B Gorontalo

Moh. Yusuf Tuloli, Arfan Utiarahman, Tandimas Febriyanto
article en

Abstract

Delays in project execution can be addressed through project control techniques such as the crash method, which aims to accelerate project duration without significantly increasing costs. This study investigates the application of the crash method in the acceleration of a Type B Terminal construction project (Phase 1) to evaluate its impact on project duration and cost. The research employs a quantitative descriptive approach, combining literature review and field observation. Data collection includes the original project schedule and cost information, followed by critical path analysis using the Critical Path Method (CPM). Based on the identified critical activities, the study applies crash analysis by reducing the duration of critical tasks and adding overtime hours, then compares various scenarios to determine the most cost-effective acceleration strategy. The results reveal that an additional 4 hours of overtime is the most efficient option, reducing the project duration by 43% while incurring the lowest total cost of Rp 3,860,600,576.59. This finding highlights that proper application of the crash method can lead to substantial time savings with manageable cost implications. In conclusion, the crash method proves to be an effective strategy for project time optimization when supported by accurate scheduling, cost analysis, and critical activity identification. The study recommends further research to validate these findings across different types of infrastructure projects using updated specifications.

Research Review Jurnal Ilmiah MultidisiplinVol. 4(1)
State University of Gorontalo (ID)
Openalex Percentile: Top 71%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analisa Penambahan Jam Lembur Kerja dengan Metode Crash Program pada Proyek Pembangunan Terminal Tipe B Gorontalo — Moh. Yusuf Tuloli, Arfan Utiarahman, et al. · Research Review Jurnal Ilmiah Multidisiplin (2025) | TGRS Research Map | TGRS