Analisis Keterlambatan Proyek Menggunakan Metode Fault Tree Analysis pada Proyek Amaris Extension Gorontalo

Construction project delays are a critical issue frequently encountered during project implementation. These delays may result from various internal factors such as labor shortages, late material deliveries, and incomplete design plans, all of which directly impact the project completion schedule. The Fault Tree Analysis (FTA) method needs to be applied to the Amaris Extension Gorontalo project to identify and mitigate delay-causing factors that pose a risk to timely project completion. The FTA method is used to identify the root causes of project delays by analyzing the basic failure factors. Data were collected through observations, interviews, and project schedules. The analysis was conducted by constructing a fault tree. This study was carried out on the Amaris Extension Gorontalo project with a duration of 365 days. The results of the study indicate that delays were primarily caused by incomplete design planning, labor shortages, and issues related to materials and execution. The Fault Tree Analysis (FTA) method successfully identified the root causes and the top events with the highest probability of occurrence in weeks 19 and 20. These findings provide a solid foundation for improving future project management.

Authors

Institutions

Publication Details

Journal
Research Review Jurnal Ilmiah Multidisiplin
Published
2025-06-28
DOI
https://doi.org/10.54923/researchreview.v4i1.182
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisis Keterlambatan Proyek Menggunakan Metode Fault Tree Analysis pada Proyek Amaris Extension Gorontalo

Arfan Utiarahman, Raul Fauzan Ishak, Apriyanto Pahrun
Research Review Jurnal Ilmiah Multidisiplin
Management and Optimization Techniques
article

Analisis Keterlambatan Proyek Menggunakan Metode Fault Tree Analysis pada Proyek Amaris Extension Gorontalo

Arfan Utiarahman, Raul Fauzan Ishak, Apriyanto Pahrun
article en

Abstract

Construction project delays are a critical issue frequently encountered during project implementation. These delays may result from various internal factors such as labor shortages, late material deliveries, and incomplete design plans, all of which directly impact the project completion schedule. The Fault Tree Analysis (FTA) method needs to be applied to the Amaris Extension Gorontalo project to identify and mitigate delay-causing factors that pose a risk to timely project completion. The FTA method is used to identify the root causes of project delays by analyzing the basic failure factors. Data were collected through observations, interviews, and project schedules. The analysis was conducted by constructing a fault tree. This study was carried out on the Amaris Extension Gorontalo project with a duration of 365 days. The results of the study indicate that delays were primarily caused by incomplete design planning, labor shortages, and issues related to materials and execution. The Fault Tree Analysis (FTA) method successfully identified the root causes and the top events with the highest probability of occurrence in weeks 19 and 20. These findings provide a solid foundation for improving future project management.

Research Review Jurnal Ilmiah MultidisiplinVol. 4(1)
State University of Gorontalo (ID)
Openalex Percentile: Top 71%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.