Pengendalian Proyek Dengan Menggunakan Metode Crash Program (Studi Kasus Pembangunan Bendungan Bulango Ulu Paket 1, Item Pekejaan Maindam, Provinsi Gorontalo)

The implementation of infrastructure development in Indonesia has grown rapidly in recent years, particularly in the context of its status as a developing country. One major project receiving attention in Gorontalo Province is the construction of the Bulango Ulu Dam. However, this project has faced delays in completion, which necessitates an in-depth analysis to optimize both time and cost. This study aims to analyze the project’s work network to identify the critical path and evaluate time and cost efficiency through the application of a crash program using additional overtime hours. The research was conducted at several project locations: Tulova Village, Owata Village, and Mongiilo Village in Bone Bolango Regency, Gorontalo Province. The study employed the crash program method and utilized Microsoft Project and Microsoft Excel for data processing. These tools supported the identification of critical tasks and the analysis of overtime productivity, crash duration, cost slope, and post-crash program time and cost efficiency. The analysis revealed that critical tasks in the Bulango Ulu Dam construction include drilling and grouting, stockpile work, dam top miscellaneous work, cleaning, and jetty trash boom installation. Time efficiency resulting from overtime additions was found to be: 10% (1 hour), 16.90% (2 hours), 22.62% (3 hours), 26.67% (4 hours), and 30% (5 hours). Meanwhile, cost efficiency peaked at 2.58% with 4 hours of overtime. These findings suggest that the optimal scenario for time and cost efficiency in hoarding work is achieved by adding 4 hours of overtime.

Authors

Institutions

Publication Details

Journal
Research Review Jurnal Ilmiah Multidisiplin
Published
2025-06-27
DOI
https://doi.org/10.54923/researchreview.v4i1.158
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Pengendalian Proyek Dengan Menggunakan Metode Crash Program (Studi Kasus Pembangunan Bendungan Bulango Ulu Paket 1, Item Pekejaan Maindam, Provinsi Gorontalo)

Mohammad Yusuf Tuloli, Arfan Usman Sumaga, Mudatsir
Research Review Jurnal Ilmiah Multidisiplin
Occupational Health and Safety Management
article

Pengendalian Proyek Dengan Menggunakan Metode Crash Program (Studi Kasus Pembangunan Bendungan Bulango Ulu Paket 1, Item Pekejaan Maindam, Provinsi Gorontalo)

Mohammad Yusuf Tuloli, Arfan Usman Sumaga, Mudatsir
article en

Abstract

The implementation of infrastructure development in Indonesia has grown rapidly in recent years, particularly in the context of its status as a developing country. One major project receiving attention in Gorontalo Province is the construction of the Bulango Ulu Dam. However, this project has faced delays in completion, which necessitates an in-depth analysis to optimize both time and cost. This study aims to analyze the project’s work network to identify the critical path and evaluate time and cost efficiency through the application of a crash program using additional overtime hours. The research was conducted at several project locations: Tulova Village, Owata Village, and Mongiilo Village in Bone Bolango Regency, Gorontalo Province. The study employed the crash program method and utilized Microsoft Project and Microsoft Excel for data processing. These tools supported the identification of critical tasks and the analysis of overtime productivity, crash duration, cost slope, and post-crash program time and cost efficiency. The analysis revealed that critical tasks in the Bulango Ulu Dam construction include drilling and grouting, stockpile work, dam top miscellaneous work, cleaning, and jetty trash boom installation. Time efficiency resulting from overtime additions was found to be: 10% (1 hour), 16.90% (2 hours), 22.62% (3 hours), 26.67% (4 hours), and 30% (5 hours). Meanwhile, cost efficiency peaked at 2.58% with 4 hours of overtime. These findings suggest that the optimal scenario for time and cost efficiency in hoarding work is achieved by adding 4 hours of overtime.

Research Review Jurnal Ilmiah MultidisiplinVol. 4(1)
State University of Gorontalo (ID)
Openalex Percentile: Top 71%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Pengendalian Proyek Dengan Menggunakan Metode Crash Program (Studi Kasus Pembangunan Bendungan Bulango Ulu Paket 1, Item Pekejaan Maindam, Provinsi Gorontalo) — Mohammad Yusuf Tuloli, Arfan Usman Sumaga, et al. · Research Review Jurnal Ilmiah Multidisiplin (2025) | TGRS Research Map | TGRS