Analysis Of Comparative Cost Efficiency Of Conventional And Semi System Formwork Methods In Wall Buildings (Case Study: Bank Indonesia Gresik Area Project)

The Bank Indonesia Gresik project, especially in the Khazanah area, has high formwork requirements for the wall elements. Payment to subcontractors is made without down payment and using a 45-day term system after invoice and work progress. The purpose of this study is to compare the cost and time efficiency between conventional and semi-system formwork methods. The research method used is the comparative method, with cost and time analysis on 11,736.48 m² of wall work. Conventional formwork uses materials such as plywood and meranti wood, while the semi-system method uses hollow and phenolic frames. The results showed that the cost of the conventional method was IDR 2,438,396,000, while the semi-system method was only IDR 1,425,760,695. In terms of time, the conventional method takes 187 days, while the semi-system method only takes 131 days. The semi-system method provides time efficiency of 29.95% and cost efficiency of up to 41.53%. In conclusion, the semi-system formwork method is more efficient in terms of cost and time than the conventional method, so it is more feasible to apply to the wall formwork work of the Bank Indonesia Gresik Area Project.

Authors

Institutions

Publication Details

Journal
Publikasi Riset Orientasi Teknik Sipil (Proteksi)
Published
2025-06-30
DOI
https://doi.org/10.26740/proteksi.v7n1.p59-66
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis Of Comparative Cost Efficiency Of Conventional And Semi System Formwork Methods In Wall Buildings (Case Study: Bank Indonesia Gresik Area Project)

JENNY SEPTYA DAMAI NAVIDA, ST. Maulidya Octaviani B, ST. Wisnu Abiarto N
Publikasi Riset Orientasi Teknik Sipil (Proteksi)
BIM and Construction Integration
article

Analysis Of Comparative Cost Efficiency Of Conventional And Semi System Formwork Methods In Wall Buildings (Case Study: Bank Indonesia Gresik Area Project)

JENNY SEPTYA DAMAI NAVIDA, ST. Maulidya Octaviani B, ST. Wisnu Abiarto N
article en

Abstract

The Bank Indonesia Gresik project, especially in the Khazanah area, has high formwork requirements for the wall elements. Payment to subcontractors is made without down payment and using a 45-day term system after invoice and work progress. The purpose of this study is to compare the cost and time efficiency between conventional and semi-system formwork methods. The research method used is the comparative method, with cost and time analysis on 11,736.48 m² of wall work. Conventional formwork uses materials such as plywood and meranti wood, while the semi-system method uses hollow and phenolic frames. The results showed that the cost of the conventional method was IDR 2,438,396,000, while the semi-system method was only IDR 1,425,760,695. In terms of time, the conventional method takes 187 days, while the semi-system method only takes 131 days. The semi-system method provides time efficiency of 29.95% and cost efficiency of up to 41.53%. In conclusion, the semi-system formwork method is more efficient in terms of cost and time than the conventional method, so it is more feasible to apply to the wall formwork work of the Bank Indonesia Gresik Area Project.

Publikasi Riset Orientasi Teknik Sipil (Proteksi)Vol. 7(1)
Universitas Dr. Soetomo (ID)
Openalex Percentile: Top 79%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis Of Comparative Cost Efficiency Of Conventional And Semi System Formwork Methods In Wall Buildings (Case Study: Bank Indonesia Gresik Area Project) — JENNY SEPTYA DAMAI NAVIDA, ST. Maulidya Octaviani B, et al. · Publikasi Riset Orientasi Teknik Sipil (Proteksi) (2025) | TGRS Research Map | TGRS