A-priori accuracy assessment of tracing the cut-through in the vertical plane during the construction of the haulage drift in the "Grot" mine

Mining projects for the exploitation of the grade ores encompass specific technical and technological solutions that are a consequence of the characteristic spatial position and geometry of the ore deposit, existing mining works, natural and artificial objects, and terrain relief. To realize the mining project, a series of mining and surveying tasks must be carried out in the pre-project and project phases of exploitation, as well as during the construction of mine facilities and the excavation of mineral materials. Among the various mining and surveying tasks that follow project implementation, the tracing of the cut-through or cross-cuts, between existing mine tasks is often a crucial step. For the successful execution of these tasks, it is necessary to perform an a priori assessment of the accuracy of the cut-through in order to define the required precision for the measurement/monitoring process, and based on that, determine the appropriate equipment and measurement method. This paper presents a priori assessment of the accuracy of marking the cut-through in the vertical plane during the construction of the haulage drift on the IX horizon of the "Grot" lead and zinc mine.

Authors

Publication Details

Journal
Podzemni radovi
Published
2025-01-01
DOI
https://doi.org/10.5937/podrad2501175g
Primary Topic
Geotechnical and Geomechanical Engineering
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A-priori accuracy assessment of tracing the cut-through in the vertical plane during the construction of the haulage drift in the "Grot" mine

Zoran Gojković, Aleksandar Milutinović, Aleksandar Ganić, Aleksandar Đorđević et al.
Podzemni radovi
Geotechnical and Geomechanical Engineering
article

A-priori accuracy assessment of tracing the cut-through in the vertical plane during the construction of the haulage drift in the "Grot" mine

Zoran Gojković, Aleksandar Milutinović, Aleksandar Ganić, Aleksandar Đorđević, Nevena Đurđev
article en

Abstract

Mining projects for the exploitation of the grade ores encompass specific technical and technological solutions that are a consequence of the characteristic spatial position and geometry of the ore deposit, existing mining works, natural and artificial objects, and terrain relief. To realize the mining project, a series of mining and surveying tasks must be carried out in the pre-project and project phases of exploitation, as well as during the construction of mine facilities and the excavation of mineral materials. Among the various mining and surveying tasks that follow project implementation, the tracing of the cut-through or cross-cuts, between existing mine tasks is often a crucial step. For the successful execution of these tasks, it is necessary to perform an a priori assessment of the accuracy of the cut-through in order to define the required precision for the measurement/monitoring process, and based on that, determine the appropriate equipment and measurement method. This paper presents a priori assessment of the accuracy of marking the cut-through in the vertical plane during the construction of the haulage drift on the IX horizon of the "Grot" lead and zinc mine.

Podzemni radovi(46)
Ministarstvo Prosvete, Nauke i Tehnološkog Razvoja
Openalex Percentile: Top 79%
Geotechnical and Geomechanical Engineering
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.