A Comparative Study of Quantity and Scheduling Using 4D BIM and Conventional Methods in Column, Beam, and Slab Construction

Inadequacies in the conceptualization and assessment of construction scheduling frameworks can disrupt the epistemic continuity of project execution, thereby undermining procedural coherence and operational efficiency. Accurate and detailed material quantity planning is essential to ensure precise resource forecasting and the development of efficient and reliable construction schedules. This research investigates the role of methodological selection in the accuracy and efficiency of construction planning, with a particular emphasis on material quantification and scheduling outcomes through this comparative framework. The methodological approach undertaken in this study involves quantity surveying practices through the application of two modelling-based techniques, namely CAD-Revit and CAD-Conventional. For construction-shop drawing documentation as the primary data source, material quantities derived from each method serve as the basis for schedule development. This process culminates in the integration of 4D Building Information Modelling to facilitate the temporal visualisation of construction sequences, which supports a more comprehensive evaluation of the implications associated with each quantity derivation method on the accuracy of project planning. The comparative analysis of material quantities derived from the two methods revealed significant fluctuations, with the CAD-Revit approach demonstrating greater efficiency in material usage. This variation was further reflected in the scheduling outcomes, where the 4D BIM methodology indicated divergent timelines for the completion of structural component progress across different floors.

Authors

Institutions

Publication Details

Journal
JURNAL TEKNIK SIPIL CENDEKIA (JTSC)
Published
2025-07-26
DOI
https://doi.org/10.51988/jtsc.v6i2.290
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Comparative Study of Quantity and Scheduling Using 4D BIM and Conventional Methods in Column, Beam, and Slab Construction

I Nyoman Dita Pahang Putra, Griselda Junianda Velantika, Risal Muzaffar
JURNAL TEKNIK SIPIL CENDEKIA (JTSC)
BIM and Construction Integration
article

A Comparative Study of Quantity and Scheduling Using 4D BIM and Conventional Methods in Column, Beam, and Slab Construction

I Nyoman Dita Pahang Putra, Griselda Junianda Velantika, Risal Muzaffar
article en

Abstract

Inadequacies in the conceptualization and assessment of construction scheduling frameworks can disrupt the epistemic continuity of project execution, thereby undermining procedural coherence and operational efficiency. Accurate and detailed material quantity planning is essential to ensure precise resource forecasting and the development of efficient and reliable construction schedules. This research investigates the role of methodological selection in the accuracy and efficiency of construction planning, with a particular emphasis on material quantification and scheduling outcomes through this comparative framework. The methodological approach undertaken in this study involves quantity surveying practices through the application of two modelling-based techniques, namely CAD-Revit and CAD-Conventional. For construction-shop drawing documentation as the primary data source, material quantities derived from each method serve as the basis for schedule development. This process culminates in the integration of 4D Building Information Modelling to facilitate the temporal visualisation of construction sequences, which supports a more comprehensive evaluation of the implications associated with each quantity derivation method on the accuracy of project planning. The comparative analysis of material quantities derived from the two methods revealed significant fluctuations, with the CAD-Revit approach demonstrating greater efficiency in material usage. This variation was further reflected in the scheduling outcomes, where the 4D BIM methodology indicated divergent timelines for the completion of structural component progress across different floors.

JURNAL TEKNIK SIPIL CENDEKIA (JTSC)Vol. 6(2)
University of Pembangunan Nasional Veteran Jawa Timur (ID)
Openalex Percentile: Top 81%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A Comparative Study of Quantity and Scheduling Using 4D BIM and Conventional Methods in Column, Beam, and Slab Construction — I Nyoman Dita Pahang Putra, Griselda Junianda Velantika, et al. · JURNAL TEKNIK SIPIL CENDEKIA (JTSC) (2025) | TGRS Research Map | TGRS