Feasibility of a Program Delay Claims Scheme: Synergistic Effect and Risk–Cost Optimization

In an individual project, the delay of a contractor does not affect third parties other than the owner. However, this is not the case for a program with multiple projects. In this case, a delay to a previous project can cause work idleness losses for subsequent projects. However, if a delay claims scheme is applied to an individual project, the program owner would be responsible for the work idleness losses through no fault of their own, such as paying financial compensation to the contractor and extending the construction period, which is clearly unreasonable. Although some studies have identified this problem and proposed reasonable solutions, they have not focused on the feasibility of a program delay claims scheme. Therefore, it is not known whether a program delay claims scheme would help program owners and contractors reduce their risk cost. To solve this problem, from the perspective of the synergistic effect and risk-cost optimization, this study introduces the concept of a special free float and optimizes its calculation method. A program delay-response mechanism and risk-cost optimization model of program participants are established using the nondominated sorting genetic Algorithm III (NSGA-III) algorithm. The results showed that under the synergistic effect, program owners and contractors can achieve a win–win situation, and the program delay claims scheme is both reasonable and feasible. This study lays a theoretical foundation for cooperation between program owners and contractors and assists program owners in the management of delays and subsequent claims.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2025-07-26
DOI
https://doi.org/10.1061/jcemd4.coeng-16532
Primary Topic
Software Reliability and Analysis Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Feasibility of a Program Delay Claims Scheme: Synergistic Effect and Risk–Cost Optimization

Ting Lu, Xu Chen, Ying Zhao, Jingchun Feng
Journal of Construction Engineering and Management
Software Reliability and Analysis Research
article

Feasibility of a Program Delay Claims Scheme: Synergistic Effect and Risk–Cost Optimization

Ting Lu, Xu Chen, Ying Zhao, Jingchun Feng
article en

Abstract

In an individual project, the delay of a contractor does not affect third parties other than the owner. However, this is not the case for a program with multiple projects. In this case, a delay to a previous project can cause work idleness losses for subsequent projects. However, if a delay claims scheme is applied to an individual project, the program owner would be responsible for the work idleness losses through no fault of their own, such as paying financial compensation to the contractor and extending the construction period, which is clearly unreasonable. Although some studies have identified this problem and proposed reasonable solutions, they have not focused on the feasibility of a program delay claims scheme. Therefore, it is not known whether a program delay claims scheme would help program owners and contractors reduce their risk cost. To solve this problem, from the perspective of the synergistic effect and risk-cost optimization, this study introduces the concept of a special free float and optimizes its calculation method. A program delay-response mechanism and risk-cost optimization model of program participants are established using the nondominated sorting genetic Algorithm III (NSGA-III) algorithm. The results showed that under the synergistic effect, program owners and contractors can achieve a win–win situation, and the program delay claims scheme is both reasonable and feasible. This study lays a theoretical foundation for cooperation between program owners and contractors and assists program owners in the management of delays and subsequent claims.

Journal of Construction Engineering and ManagementVol. 151(10)
Hohai University (CN), Shandong University of Political Science and Law (CN)
Openalex Percentile: Top 82%
Software Reliability and Analysis Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Feasibility of a Program Delay Claims Scheme: Synergistic Effect and Risk–Cost Optimization — Ting Lu, Xu Chen, et al. · Journal of Construction Engineering and Management (2025) | TGRS Research Map | TGRS