COST AND TIME EVALUATION WITH TIME COST TRADE OFF (TCTO) METHOD IN TIJ TUNNEL CONSTRUCTION (JOYOBOYO INTERMODA TERMINAL)

Infrastructure development is one of the main indicators in supporting city development, especially in metropolitan areas such as Surabaya. One of the strategic projects being designed is the construction of a pedestrian tunnel that will connect the Joyoboyo Intermodal Terminal (TIJ) with the Surabaya Zoo (KBS). This study aims to optimize the cost and completion time of the project through a case study of the construction of a pedestrian tunnel between TIJ and KBS. Based on the contract's provisions, this project is scheduled to be completed within 156 calendar days, starting on May 30 2024, and ending on November 21, 2024. As an effort to optimize the cost and duration of project implementation, the Time Cost Trade Off (TCTO) approach is used. Through the application of this method, the results obtained that the addition of working time (overtime) for 3 hours per day on the work item of reinforced concrete walls with a thickness of 60 cm and concrete quality Fc'35 MPa (PC 450) is quite effective in accelerating project completion from 156 days to 145 days. In addition, the optimum cost generated is Rp14,116,469,946.62, which means a cost saving of Rp43,510,269.42 compared to the normal cost. From the analysis results, the project time efficiency is 0.31%.

Authors

Institutions

Publication Details

Journal
JURNAL TEKNIK SIPIL CENDEKIA (JTSC)
Published
2025-07-26
DOI
https://doi.org/10.51988/jtsc.v6i2.297
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

COST AND TIME EVALUATION WITH TIME COST TRADE OFF (TCTO) METHOD IN TIJ TUNNEL CONSTRUCTION (JOYOBOYO INTERMODA TERMINAL)

Masca Indra Triana, Ahmad Zaenul Baharnur, Putri Suci Mawaritza
JURNAL TEKNIK SIPIL CENDEKIA (JTSC)
BIM and Construction Integration
article

COST AND TIME EVALUATION WITH TIME COST TRADE OFF (TCTO) METHOD IN TIJ TUNNEL CONSTRUCTION (JOYOBOYO INTERMODA TERMINAL)

Masca Indra Triana, Ahmad Zaenul Baharnur, Putri Suci Mawaritza
article en

Abstract

Infrastructure development is one of the main indicators in supporting city development, especially in metropolitan areas such as Surabaya. One of the strategic projects being designed is the construction of a pedestrian tunnel that will connect the Joyoboyo Intermodal Terminal (TIJ) with the Surabaya Zoo (KBS). This study aims to optimize the cost and completion time of the project through a case study of the construction of a pedestrian tunnel between TIJ and KBS. Based on the contract's provisions, this project is scheduled to be completed within 156 calendar days, starting on May 30 2024, and ending on November 21, 2024. As an effort to optimize the cost and duration of project implementation, the Time Cost Trade Off (TCTO) approach is used. Through the application of this method, the results obtained that the addition of working time (overtime) for 3 hours per day on the work item of reinforced concrete walls with a thickness of 60 cm and concrete quality Fc'35 MPa (PC 450) is quite effective in accelerating project completion from 156 days to 145 days. In addition, the optimum cost generated is Rp14,116,469,946.62, which means a cost saving of Rp43,510,269.42 compared to the normal cost. From the analysis results, the project time efficiency is 0.31%.

JURNAL TEKNIK SIPIL CENDEKIA (JTSC)Vol. 6(2)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 81%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

COST AND TIME EVALUATION WITH TIME COST TRADE OFF (TCTO) METHOD IN TIJ TUNNEL CONSTRUCTION (JOYOBOYO INTERMODA TERMINAL) — Masca Indra Triana, Ahmad Zaenul Baharnur, et al. · JURNAL TEKNIK SIPIL CENDEKIA (JTSC) (2025) | TGRS Research Map | TGRS