Non-conformance and Correction Costs in Construction: Insights from Actual Practice

The corrective actions applied to non-conforming products—commonly termed rework—can substantially erode a construction organization's performance, productivity, and profitability. Yet empirical knowledge of the actual cost of rework in the field remains sparse. This study quantifies rework costs across 12 completed transport-infrastructure projects (with a total contract value of AU$2 billion) delivered via an alliance-based program. We find that 61 % of all non-conformances (656 of 1,064) required rework, with an average rework cost equal to 0.34 % of each project's contract value. Notably, a single project accounted for 57% of the total rework expenditure and 31% of the issued non-conformances. This paper thus (1) offers new, data-driven insights into the actual costs of rework on major infrastructure works and (2) demonstrates that rework incidence and its financial impact vary widely across projects.

Authors

Institutions

Publication Details

Journal
IEEE Engineering Management Review
Published
2025-01-01
DOI
https://doi.org/10.1109/emr.2025.3591478
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Non-conformance and Correction Costs in Construction: Insights from Actual Practice

Peter E.D. Love, Jane Matthews
IEEE Engineering Management Review
Construction Project Management and Performance
article

Non-conformance and Correction Costs in Construction: Insights from Actual Practice

Peter E.D. Love, Jane Matthews
article en

Abstract

The corrective actions applied to non-conforming products—commonly termed rework—can substantially erode a construction organization's performance, productivity, and profitability. Yet empirical knowledge of the actual cost of rework in the field remains sparse. This study quantifies rework costs across 12 completed transport-infrastructure projects (with a total contract value of AU$2 billion) delivered via an alliance-based program. We find that 61 % of all non-conformances (656 of 1,064) required rework, with an average rework cost equal to 0.34 % of each project's contract value. Notably, a single project accounted for 57% of the total rework expenditure and 31% of the issued non-conformances. This paper thus (1) offers new, data-driven insights into the actual costs of rework on major infrastructure works and (2) demonstrates that rework incidence and its financial impact vary widely across projects.

IEEE Engineering Management Review
Deakin University (AU), Curtin University (AU)
Openalex Percentile: Top 79%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Non-conformance and Correction Costs in Construction: Insights from Actual Practice — Peter E.D. Love, Jane Matthews · IEEE Engineering Management Review (2025) | TGRS Research Map | TGRS