REVIEW OF WORK USING THE EARNED VALUE ANALYSIS METHOD ON THE PLTG GRATI TO PESANGGARAN BALI PROJECT

In construction projects, acceleration work has significant relevance in the modern construction industry. The Grati Gas Power Plant (PLTG) Relocation project to Pesanggaran Bali has a work implementation period of 460 days or 15 months. However, the Job Owner requested to complete it with a duration of 10 months. This study uses the Earned Value Analysis (EVA) method with direct observation in accelerating the work. By accelerating the work on the Grati Gas Power Plant (PLTG) Relocation project to Pesanggaran Bali, it can be estimated that the work can be completed on time according to the job owner's request, which is 10 months. Regarding the cost implications that occur due to the acceleration of the work, the estimated expenditure is smaller than the planned budget so that the project is estimated to have potential profit. And also make an estimated calculation in carrying out the acceleration of the work and record all costs incurred in implementing the acceleration of the work, so that the costs incurred (Actual Cost) are not greater than the budget planned at the beginning of the work or Budget At Complection (BAC).

Authors

Institutions

Publication Details

Journal
Jurnal Ilmiah METADATA
Published
2025-07-21
DOI
https://doi.org/10.47652/metadata.v7i2.620
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

REVIEW OF WORK USING THE EARNED VALUE ANALYSIS METHOD ON THE PLTG GRATI TO PESANGGARAN BALI PROJECT

Ike Oktaviani, Dedek Catur Amung Saputra, Jon Putra, Hendry Sampurna et al.
Jurnal Ilmiah METADATA
Mining Techniques and Economics
article

REVIEW OF WORK USING THE EARNED VALUE ANALYSIS METHOD ON THE PLTG GRATI TO PESANGGARAN BALI PROJECT

Ike Oktaviani, Dedek Catur Amung Saputra, Jon Putra, Hendry Sampurna, Ngir Tjuk Hirwo
article en

Abstract

In construction projects, acceleration work has significant relevance in the modern construction industry. The Grati Gas Power Plant (PLTG) Relocation project to Pesanggaran Bali has a work implementation period of 460 days or 15 months. However, the Job Owner requested to complete it with a duration of 10 months. This study uses the Earned Value Analysis (EVA) method with direct observation in accelerating the work. By accelerating the work on the Grati Gas Power Plant (PLTG) Relocation project to Pesanggaran Bali, it can be estimated that the work can be completed on time according to the job owner's request, which is 10 months. Regarding the cost implications that occur due to the acceleration of the work, the estimated expenditure is smaller than the planned budget so that the project is estimated to have potential profit. And also make an estimated calculation in carrying out the acceleration of the work and record all costs incurred in implementing the acceleration of the work, so that the costs incurred (Actual Cost) are not greater than the budget planned at the beginning of the work or Budget At Complection (BAC).

Jurnal Ilmiah METADATAVol. 7(2)
Institut Teknologi Budi Utomo (ID)
Openalex Percentile: Top 80%
Mining Techniques and Economics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

REVIEW OF WORK USING THE EARNED VALUE ANALYSIS METHOD ON THE PLTG GRATI TO PESANGGARAN BALI PROJECT — Ike Oktaviani, Dedek Catur Amung Saputra, et al. · Jurnal Ilmiah METADATA (2025) | TGRS Research Map | TGRS