AI-Powered Forecasting of Environmental Impacts and Construction Costs to Enhance Project Management in Highway Projects

The accurate early-stage estimation of environmental load (EL) and construction cost (CC) in road infrastructure projects remains a significant challenge, constrained by limited data and the complexity of construction activities. To address this, our study proposes a machine learning-based predictive framework utilizing artificial neural networks (ANNs) and deep neural networks (DNNs), enhanced by autoencoder-driven feature selection. A structured dataset of 150 completed national road projects in South Korea was compiled, covering both planning and design phases. The database focused on 19 high-impact sub-work types to reduce noise and improve prediction precision. A hybrid imputation approach—combining mean substitution with random forest regression—was applied to handle 4.47% missing data in the design-phase inputs, reducing variance by up to 5% and improving data stability. Dimensionality reduction via autoencoder retained 16 core variables, preserving 97% of explanatory power while minimizing redundancy. ANN models benefited from cross-validation and hyperparameter tuning, achieving consistent performance across training and validation sets without overfitting (MSE = 0.06, RMSE = 0.24). The optimal ANN yielded average error rates of 29.8% for EL and 21.0% for CC at the design stage. DNN models, with their deeper architectures and dropout regularization, further improved performance—achieving 27.1% (EL) and 17.0% (CC) average error rates at the planning stage and 24.0% (EL) and 14.6% (CC) at the design stage. These results met all predefined accuracy thresholds, underscoring the DNN’s advantage in handling complex, high-variance data while the ANN excelled in structured cost prediction. Overall, the synergy between deep learning and autoencoder-based feature selection offers a scalable and data-informed approach for enhancing early-stage environmental and economic assessments in road infrastructure planning—supporting more sustainable and efficient project management.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-07-19
DOI
https://doi.org/10.3390/buildings15142546
Citations
3
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
3.02
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

AI-Powered Forecasting of Environmental Impacts and Construction Costs to Enhance Project Management in Highway Projects

Joon-Soo Kim
3 citations
Buildings
BIM and Construction Integration
3.02
article

AI-Powered Forecasting of Environmental Impacts and Construction Costs to Enhance Project Management in Highway Projects

Joon-Soo Kim
article en
3 citations

Abstract

The accurate early-stage estimation of environmental load (EL) and construction cost (CC) in road infrastructure projects remains a significant challenge, constrained by limited data and the complexity of construction activities. To address this, our study proposes a machine learning-based predictive framework utilizing artificial neural networks (ANNs) and deep neural networks (DNNs), enhanced by autoencoder-driven feature selection. A structured dataset of 150 completed national road projects in South Korea was compiled, covering both planning and design phases. The database focused on 19 high-impact sub-work types to reduce noise and improve prediction precision. A hybrid imputation approach—combining mean substitution with random forest regression—was applied to handle 4.47% missing data in the design-phase inputs, reducing variance by up to 5% and improving data stability. Dimensionality reduction via autoencoder retained 16 core variables, preserving 97% of explanatory power while minimizing redundancy. ANN models benefited from cross-validation and hyperparameter tuning, achieving consistent performance across training and validation sets without overfitting (MSE = 0.06, RMSE = 0.24). The optimal ANN yielded average error rates of 29.8% for EL and 21.0% for CC at the design stage. DNN models, with their deeper architectures and dropout regularization, further improved performance—achieving 27.1% (EL) and 17.0% (CC) average error rates at the planning stage and 24.0% (EL) and 14.6% (CC) at the design stage. These results met all predefined accuracy thresholds, underscoring the DNN’s advantage in handling complex, high-variance data while the ANN excelled in structured cost prediction. Overall, the synergy between deep learning and autoencoder-based feature selection offers a scalable and data-informed approach for enhancing early-stage environmental and economic assessments in road infrastructure planning—supporting more sustainable and efficient project management.

BuildingsVol. 15(14)
Korea Institute of Civil Engineering and Building Technology (KR)
Openalex Percentile: Top 9%
BIM and Construction Integration
3.02
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

AI-Powered Forecasting of Environmental Impacts and Construction Costs to Enhance Project Management in Highway Projects — Joon-Soo Kim · Buildings (2025) | TGRS Research Map | TGRS