Challenges in pricing preliminaries costs for contractors: An Australian case study

Abstract The accurate estimation of project costs is pivotal for the ongoing financial success of construction companies. Despite the clear definition of direct costs in tendering information, indirect costs (also known as project overheads and preliminaries) are often overlooked or underestimated. These costs are influenced by various factors, including company resource availability, site and project characteristics, contractual conditions and procurement methods. The pricing of preliminaries is a complex task, and the varying nature of these costs, coupled with the lack of transparency in current pricing practices, can lead to significant discrepancies in tender pricing. The challenge is to identify what should be included in preliminaries and arrive at a value in practice. This research has explored how contractors’ estimating departments address the complexities of pricing preliminaries for building and civil infrastructure works, particularly considering stringent contractual requirements and post-pandemic construction market disruptions. Through a literature review and an online survey of 30 senior estimators from major contractors, addressing 18 questions, the research sought to understand current practices, differing approaches and metrics employed in pricing preliminaries during the tendering stage. The multifaceted nature of preliminary studies was examined, offering a structured analysis of their categorisation, estimation methods, associated challenges and the impact of project delivery methods. The findings reveal that each contractor processes the pricing of preliminaries using certain tendering gateways and a variety of different metrics. This indicates that systematic risk and pricing models for contractors may lack a justifiable basis, with existing pricing models facing acceptance challenges across different contractors.

Authors

Institutions

Publication Details

Journal
Organization Technology and Management in Construction An International Journal
Published
2025-01-01
DOI
https://doi.org/10.2478/otmcj-2025-0008
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Challenges in pricing preliminaries costs for contractors: An Australian case study

Paulo Vaz‐Serra, Timothy O’Leary
1 links
Organization Technology and Management in Construction An International Journal
Construction Project Management and Performance
article

Challenges in pricing preliminaries costs for contractors: An Australian case study

Paulo Vaz‐Serra, Timothy O’Leary
article en

Abstract

Abstract The accurate estimation of project costs is pivotal for the ongoing financial success of construction companies. Despite the clear definition of direct costs in tendering information, indirect costs (also known as project overheads and preliminaries) are often overlooked or underestimated. These costs are influenced by various factors, including company resource availability, site and project characteristics, contractual conditions and procurement methods. The pricing of preliminaries is a complex task, and the varying nature of these costs, coupled with the lack of transparency in current pricing practices, can lead to significant discrepancies in tender pricing. The challenge is to identify what should be included in preliminaries and arrive at a value in practice. This research has explored how contractors’ estimating departments address the complexities of pricing preliminaries for building and civil infrastructure works, particularly considering stringent contractual requirements and post-pandemic construction market disruptions. Through a literature review and an online survey of 30 senior estimators from major contractors, addressing 18 questions, the research sought to understand current practices, differing approaches and metrics employed in pricing preliminaries during the tendering stage. The multifaceted nature of preliminary studies was examined, offering a structured analysis of their categorisation, estimation methods, associated challenges and the impact of project delivery methods. The findings reveal that each contractor processes the pricing of preliminaries using certain tendering gateways and a variety of different metrics. This indicates that systematic risk and pricing models for contractors may lack a justifiable basis, with existing pricing models facing acceptance challenges across different contractors.

Organization Technology and Management in Construction An International JournalVol. 17(1)
The University of Melbourne (AU)
Openalex Percentile: Top 80%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Challenges in pricing preliminaries costs for contractors: An Australian case study — Paulo Vaz‐Serra, Timothy O’Leary · Organization Technology and Management in Construction An International Journal (2025) | TGRS Research Map | TGRS