Investigating the dynamics of delays in public building projects in Uganda

This study investigates the dynamics of delays in public building projects in Uganda, with a focus on identifying the types, causes, and impacts of delays on project timelines and outcomes. A mixed-methods approach was employed, combining quantitative data from surveys and qualitative insights from interviews with key stakeholders, including project managers, engineers, and contractors. The status of the projects for instance were, 51.4% of public building projects were ongoing, with over 47% facing delays extending between 6 to 12 months, and 38.9% delayed beyond 12 months. The findings reveal that weather-related delays (25%), material procurement issues (19.4%), and labour shortages (26.4%) are the most significant contributors to project delays. Additional factors such as design changes (15.3%) and regulatory delays, including permitting and approval processes (5.6%), also play a crucial role. The research shows that these delays lead to substantial socio-economic impacts, including increased project costs, extended timelines, and delayed service delivery, ultimately affecting infrastructure development in Uganda. To address these challenges, the study recommends adopting advanced project management tools, such as the Critical Path Method (CPM) and Time Impact Analysis (TIA), integrating accurate weather forecasting into project planning, improving procurement systems, and streamlining regulatory frameworks. The research contributes original insights into the specific delay factors in fast-urbanizing cities like Mbarara and suggests further studies on integrating smart technologies to mitigate delays.

Authors

Publication Details

Journal
KIU journal of science engineering and technology
Published
2025-05-25
DOI
https://doi.org/10.59568/kjset-2025-4-1-03
Primary Topic
Public-Private Partnership Projects
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Investigating the dynamics of delays in public building projects in Uganda

Ernest O. Nnadi, Rhita Bamwesigye, Daniel Mogaka
KIU journal of science engineering and technology
Public-Private Partnership Projects
article

Investigating the dynamics of delays in public building projects in Uganda

Ernest O. Nnadi, Rhita Bamwesigye, Daniel Mogaka
article en

Abstract

This study investigates the dynamics of delays in public building projects in Uganda, with a focus on identifying the types, causes, and impacts of delays on project timelines and outcomes. A mixed-methods approach was employed, combining quantitative data from surveys and qualitative insights from interviews with key stakeholders, including project managers, engineers, and contractors. The status of the projects for instance were, 51.4% of public building projects were ongoing, with over 47% facing delays extending between 6 to 12 months, and 38.9% delayed beyond 12 months. The findings reveal that weather-related delays (25%), material procurement issues (19.4%), and labour shortages (26.4%) are the most significant contributors to project delays. Additional factors such as design changes (15.3%) and regulatory delays, including permitting and approval processes (5.6%), also play a crucial role. The research shows that these delays lead to substantial socio-economic impacts, including increased project costs, extended timelines, and delayed service delivery, ultimately affecting infrastructure development in Uganda. To address these challenges, the study recommends adopting advanced project management tools, such as the Critical Path Method (CPM) and Time Impact Analysis (TIA), integrating accurate weather forecasting into project planning, improving procurement systems, and streamlining regulatory frameworks. The research contributes original insights into the specific delay factors in fast-urbanizing cities like Mbarara and suggests further studies on integrating smart technologies to mitigate delays.

KIU journal of science engineering and technologyVol. 4(1)
Openalex Percentile: Top 74%
Public-Private Partnership Projects
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.