Causes of Building Permit Delays: A Case Study of a Sri Lankan Local Government Authority

Although the construction sector plays a crucial role in driving economic growth and ensuring societal well-being, construction delays within the sector remain a significant challenge in both developed and developing countries. In Sri Lanka, the construction industry is particularly affected by delays in building permit issuance. Yet, recent research addressing this issue within the Sri Lankan context remains limited. Therefore, this study aims to investigate the causes of delays in building permit issuance in a selected local government authority in Sri Lanka, focusing on both administrative and architect perspectives. A qualitative approach was adopted, including focus group interviews with administrative officers, individual interviews with architects, and descriptive analysis of secondary data on building applications from 2018-2023. The findings reveal significant challenges in the permit process, with 65% of applications during 2018-2023 exceeding the stipulated 14-day processing period. Through thematic analysis, the study identified 11 administrative reasons and 9 architect-related reasons for the delay. These insights offer critical insights into inefficiencies within the current permit process and highlight the need for reform. The study recommends enhancing administrative procedures, addressing client related issues, and improving architect practices to streamline the overall building permit process and support timely project delivery.

Authors

Institutions

Publication Details

Journal
JRES.
Published
2025-06-30
DOI
https://doi.org/10.31357/jres.v22i2.8270
Primary Topic
Public-Private Partnership Projects
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Causes of Building Permit Delays: A Case Study of a Sri Lankan Local Government Authority

N. B. Sugathadasa, Ruchini Wijesuriya
JRES.
Public-Private Partnership Projects
article

Causes of Building Permit Delays: A Case Study of a Sri Lankan Local Government Authority

N. B. Sugathadasa, Ruchini Wijesuriya
article en

Abstract

Although the construction sector plays a crucial role in driving economic growth and ensuring societal well-being, construction delays within the sector remain a significant challenge in both developed and developing countries. In Sri Lanka, the construction industry is particularly affected by delays in building permit issuance. Yet, recent research addressing this issue within the Sri Lankan context remains limited. Therefore, this study aims to investigate the causes of delays in building permit issuance in a selected local government authority in Sri Lanka, focusing on both administrative and architect perspectives. A qualitative approach was adopted, including focus group interviews with administrative officers, individual interviews with architects, and descriptive analysis of secondary data on building applications from 2018-2023. The findings reveal significant challenges in the permit process, with 65% of applications during 2018-2023 exceeding the stipulated 14-day processing period. Through thematic analysis, the study identified 11 administrative reasons and 9 architect-related reasons for the delay. These insights offer critical insights into inefficiencies within the current permit process and highlight the need for reform. The study recommends enhancing administrative procedures, addressing client related issues, and improving architect practices to streamline the overall building permit process and support timely project delivery.

JRES.Vol. 22(2)
University of Sri Jayewardenepura (LK), General Sir John Kotelawala Defence University (LK)
Openalex Percentile: Top 74%
Public-Private Partnership Projects
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.