Increasing Cost Effectiveness in Cement Manufacturing Plant: A Sustainable Approach

This study investigates the consequences of improper railway wagon scheduling in a cement industry and emphasizes the advantages of opting for rail transport over roadways or other modes of transportation. Based on an in-depth site visit to a cement plant in Rajasthan and discussions with technical staff, the research identifies the critical issue of reducing demurrage costs. The paper highlights the financial losses incurred by the company due to neglecting this issue and explores potential solutions developed in collaboration with the company’s team. These solutions aim to ensure efficient wagon scheduling, thereby minimizing demurrage costs and improving overall operational efficiency.

Authors

Institutions

Publication Details

Published
2024-12-13
DOI
https://doi.org/10.1109/sustained63638.2024.11074093
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Increasing Cost Effectiveness in Cement Manufacturing Plant: A Sustainable Approach

Prateek Mittal, Govind Govind, Suvadeep Sen, Ram Kumar et al.
Resource-Constrained Project Scheduling
article

Increasing Cost Effectiveness in Cement Manufacturing Plant: A Sustainable Approach

Prateek Mittal, Govind Govind, Suvadeep Sen, Ram Kumar, Ankit Jain, Kuldeep Kuldeep, Deepak Bhardawaj
article en

Abstract

This study investigates the consequences of improper railway wagon scheduling in a cement industry and emphasizes the advantages of opting for rail transport over roadways or other modes of transportation. Based on an in-depth site visit to a cement plant in Rajasthan and discussions with technical staff, the research identifies the critical issue of reducing demurrage costs. The paper highlights the financial losses incurred by the company due to neglecting this issue and explores potential solutions developed in collaboration with the company’s team. These solutions aim to ensure efficient wagon scheduling, thereby minimizing demurrage costs and improving overall operational efficiency.

Maharashtra State Board of Technical Education (IN), Manav Rachna International Institute of Research and Studies (IN)
Responsible consumption and production
Openalex Percentile: Top 64%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.