Approach to Represent Run-of-River Hydropower Plants in the Short-Term Hydrothermal System Operation Planning

The operation planning of hydrothermal systems is characterized by high complexity due to the inherent temporal and spatial coupling of the problem. To address this complexity, the process is traditionally structured into sequential stages, each focusing on specific aspects according to its time discretization and study horizon. In the context of the Brazilian power system, these stages are referred to as long-, mid-, and short-term planning, with interdependencies formalized through a cost-to-go function. Reservoir storage is one of the main state variables in this function, linking different temporal stages. In long- and mid-term planning, hydropower plants with small reservoirs — typically designed for daily or weekly regulation — are usually modeled as run-of-river units and not considered as state variables, as they do not significantly contribute to interstage coupling. However, in short-term planning, such plants must be explicitly modeled with their corresponding reservoirs to properly account for their ability to respond to load fluctuations. This discrepancy can create challenges when coupling mid- and short-term models, as the cost-to-go function lacks forward-looking information on small reservoirs not represented in the mid-term model. This paper proposes an approach for representing small reservoirs in short-term hydrothermal operation planning. The objective is to capture short-term storage variations while imposing a condition that the final storage level matches the initial level — a necessary criterion for the plant to be treated as run-of-river in the mid-term model. The proposed approach is applied, as a case study, to the Brazilian power system.

Authors

Institutions

Publication Details

Journal
IEEE Access
Published
2025-01-01
DOI
https://doi.org/10.1109/access.2025.3589178
Primary Topic
Advanced Power Generation Technologies
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Approach to Represent Run-of-River Hydropower Plants in the Short-Term Hydrothermal System Operation Planning

André Luís Marques Marcato, Ana Paula da Silva, Tharliane Alexandre Dos Santos
IEEE Access
Advanced Power Generation Technologies
article

Approach to Represent Run-of-River Hydropower Plants in the Short-Term Hydrothermal System Operation Planning

André Luís Marques Marcato, Ana Paula da Silva, Tharliane Alexandre Dos Santos
article en

Abstract

The operation planning of hydrothermal systems is characterized by high complexity due to the inherent temporal and spatial coupling of the problem. To address this complexity, the process is traditionally structured into sequential stages, each focusing on specific aspects according to its time discretization and study horizon. In the context of the Brazilian power system, these stages are referred to as long-, mid-, and short-term planning, with interdependencies formalized through a cost-to-go function. Reservoir storage is one of the main state variables in this function, linking different temporal stages. In long- and mid-term planning, hydropower plants with small reservoirs — typically designed for daily or weekly regulation — are usually modeled as run-of-river units and not considered as state variables, as they do not significantly contribute to interstage coupling. However, in short-term planning, such plants must be explicitly modeled with their corresponding reservoirs to properly account for their ability to respond to load fluctuations. This discrepancy can create challenges when coupling mid- and short-term models, as the cost-to-go function lacks forward-looking information on small reservoirs not represented in the mid-term model. This paper proposes an approach for representing small reservoirs in short-term hydrothermal operation planning. The objective is to capture short-term storage variations while imposing a condition that the final storage level matches the initial level — a necessary criterion for the plant to be treated as run-of-river in the mid-term model. The proposed approach is applied, as a case study, to the Brazilian power system.

IEEE AccessVol. 13
Universidade Federal de Juiz de Fora (BR), Brazilian Medical Association (BR)
Coordenação de Aperfeiçoamento de Pessoal de Nível Superior
Openalex Percentile: Top 85%
Advanced Power Generation Technologies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.