ANALISIS OPTIMASI WAKTU DAN BIAYA PADA PROYEK REHABILITASI SARANA DAN PRASARANA GEDUNG SEKOLAH DENGAN METODE TIME COST TRADE OFF

Completion of delays in the implementation of field control requires alternative analysis to get the results of accelerated time that has an impact on minimum costs. This study uses the Time Cost Trade Off (TCTO) method which aims to determine the optimization of time and cost in the rehabilitation project of facilities and infrastructure for the Mojoduwur 1 Jombang Elementary School building. This method is applied by evaluating various acceleration alternatives, one of which is through the addition of time and labor on critical path activities. The results of the analysis show that the most optimal acceleration alternative is the application of 3-shift working time which is able to accelerate the project duration for 51 days or 69 days of acceleration from 120 days of normal duration. The total cost savings reached Rp25,915,887 or Rp545,155,547 from the normal cost of Rp571,071,434, thus obtaining a time efficiency of 42.5% and a cost efficiency of 4.54%. The TCTO approach with the implementation of shift work can improve the time and cost efficiency of this project.

Authors

Publication Details

Journal
Jurnal Rekayasa dan Aplikasi Teknik Sipil
Published
2025-06-30
DOI
https://doi.org/10.33752/reaktip.v5i01.9875
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS OPTIMASI WAKTU DAN BIAYA PADA PROYEK REHABILITASI SARANA DAN PRASARANA GEDUNG SEKOLAH DENGAN METODE TIME COST TRADE OFF

Totok Yulianto, Meriana Wahyu Nugroho, Amellia Intan Putri Irra Purnomo, Tiitin Sundari
Jurnal Rekayasa dan Aplikasi Teknik Sipil
Management and Optimization Techniques
article

ANALISIS OPTIMASI WAKTU DAN BIAYA PADA PROYEK REHABILITASI SARANA DAN PRASARANA GEDUNG SEKOLAH DENGAN METODE TIME COST TRADE OFF

Totok Yulianto, Meriana Wahyu Nugroho, Amellia Intan Putri Irra Purnomo, Tiitin Sundari
article en

Abstract

Completion of delays in the implementation of field control requires alternative analysis to get the results of accelerated time that has an impact on minimum costs. This study uses the Time Cost Trade Off (TCTO) method which aims to determine the optimization of time and cost in the rehabilitation project of facilities and infrastructure for the Mojoduwur 1 Jombang Elementary School building. This method is applied by evaluating various acceleration alternatives, one of which is through the addition of time and labor on critical path activities. The results of the analysis show that the most optimal acceleration alternative is the application of 3-shift working time which is able to accelerate the project duration for 51 days or 69 days of acceleration from 120 days of normal duration. The total cost savings reached Rp25,915,887 or Rp545,155,547 from the normal cost of Rp571,071,434, thus obtaining a time efficiency of 42.5% and a cost efficiency of 4.54%. The TCTO approach with the implementation of shift work can improve the time and cost efficiency of this project.

Jurnal Rekayasa dan Aplikasi Teknik SipilVol. 5(01)
Openalex Percentile: Top 74%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALISIS OPTIMASI WAKTU DAN BIAYA PADA PROYEK REHABILITASI SARANA DAN PRASARANA GEDUNG SEKOLAH DENGAN METODE TIME COST TRADE OFF — Totok Yulianto, Meriana Wahyu Nugroho, et al. · Jurnal Rekayasa dan Aplikasi Teknik Sipil (2025) | TGRS Research Map | TGRS