ANALISIS PERCEPATAN WAKTU PROYEK KONTRUKSI MENGGUNAKAN METODE TIME COST TRADE OFF (TCTO)

The implementation of project development must be calculated and arranged in such a way, both in terms of time and cost in order to achieve maximum results. Time and cost have a significant effect on the success and failure of the project. The benchmark for project success is usually seen from the short completion time with minimal costs without reducing the quality of quality. The Youth Facilities Building Development Project in Mangunreja District, Tasikmalaya Regency is indicated to have experienced delays in its implementation process. The purpose of this study is to determine the optimal time and cost generated after accelerating working hours (overtime) using the Time Cost Trade Off method, with the alternative of adding 2 working hours (overtime) on structural work that is on the critical path. Data analysis in this study uses Microsoft Project 2013 to determine the critical path. Based on the results of the calculation analysis with time cost trade off with the addition of 2 working hours (overtime) resulting in an optimal time of 127 working days from the normal duration of 150 days, an acceleration of 23 working days was obtained with a project time efficiency of 15% and resulting in an optimum cost of Rp. 5,363,375,369.06 from the normal cost of Rp. 5,448,649,000.00 there is a cost reduction of Rp. 85,273,630.94 with a cost efficiency of 1.56%.

Authors

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-02-07
DOI
https://doi.org/10.25157/jiteks.v2i1.5120
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS PERCEPATAN WAKTU PROYEK KONTRUKSI MENGGUNAKAN METODE TIME COST TRADE OFF (TCTO)

Gini Hartati, Atep Maskur, Riska Anggraeni
Jurnal Ilmiah Teknik Sipil
Occupational Health and Safety Management
article

ANALISIS PERCEPATAN WAKTU PROYEK KONTRUKSI MENGGUNAKAN METODE TIME COST TRADE OFF (TCTO)

Gini Hartati, Atep Maskur, Riska Anggraeni
article en

Abstract

The implementation of project development must be calculated and arranged in such a way, both in terms of time and cost in order to achieve maximum results. Time and cost have a significant effect on the success and failure of the project. The benchmark for project success is usually seen from the short completion time with minimal costs without reducing the quality of quality. The Youth Facilities Building Development Project in Mangunreja District, Tasikmalaya Regency is indicated to have experienced delays in its implementation process. The purpose of this study is to determine the optimal time and cost generated after accelerating working hours (overtime) using the Time Cost Trade Off method, with the alternative of adding 2 working hours (overtime) on structural work that is on the critical path. Data analysis in this study uses Microsoft Project 2013 to determine the critical path. Based on the results of the calculation analysis with time cost trade off with the addition of 2 working hours (overtime) resulting in an optimal time of 127 working days from the normal duration of 150 days, an acceleration of 23 working days was obtained with a project time efficiency of 15% and resulting in an optimum cost of Rp. 5,363,375,369.06 from the normal cost of Rp. 5,448,649,000.00 there is a cost reduction of Rp. 85,273,630.94 with a cost efficiency of 1.56%.

Jurnal Ilmiah Teknik SipilVol. 2(1)
Universitas Galuh (ID)
Openalex Percentile: Top 75%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALISIS PERCEPATAN WAKTU PROYEK KONTRUKSI MENGGUNAKAN METODE TIME COST TRADE OFF (TCTO) — Gini Hartati, Atep Maskur, et al. · Jurnal Ilmiah Teknik Sipil (2025) | TGRS Research Map | TGRS