EVALUASI PENGENDALIAN WAKTU MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) PADA PEMBANGUNAN SARANA DAN PRASARANA GEDUNG PEMUDA JUARA KABUPATEN PANGANDARAN

In general, control is a sistematic effort to determine standards that are in accordance with planning goals, design information sistems, compare implementation with standards, and analyse the possibility of deviations The analysis of the results was used to determine the extent of time control in the construction project of the Juara Youth Building in Pangandaran Regency The purpose of this study is to determine time control using the Earned Value Management (EVM) method in the construction of facilities and infrastructure of the Pangandaran Regency Champion Youth Building. This study uses data that includes the location/location of the building, RAB calculation, S curve, time schedule, progress report. Based on the results of the project performance research in weeks 1, 2, 3, 4, 5, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, to 20 SV (Schedule Variances) values are positive (+) and the results of SPI calculations are more than one (>1). However, in the 6th week, 7,8,9 in the calculation of the value of the schedule variance (Schedule Variance) has a negative value (-) and the result of the SPI calculation is less than one (<1), This shows that for the SPI value that < 1 work experienced delays and SPI that >1 work experienced acceleration while the SPI equal to 1 work was equal to the plan.

Authors

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Sipil
Published
2025-02-07
DOI
https://doi.org/10.25157/jiteks.v2i1.5126
Primary Topic
Value Engineering and Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

EVALUASI PENGENDALIAN WAKTU MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) PADA PEMBANGUNAN SARANA DAN PRASARANA GEDUNG PEMUDA JUARA KABUPATEN PANGANDARAN

Gini Hartati, Atep Maskur, Taufik Martha, Syifa Maulia
Jurnal Ilmiah Teknik Sipil
Value Engineering and Management
article

EVALUASI PENGENDALIAN WAKTU MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (EVM) PADA PEMBANGUNAN SARANA DAN PRASARANA GEDUNG PEMUDA JUARA KABUPATEN PANGANDARAN

Gini Hartati, Atep Maskur, Taufik Martha, Syifa Maulia
article en

Abstract

In general, control is a sistematic effort to determine standards that are in accordance with planning goals, design information sistems, compare implementation with standards, and analyse the possibility of deviations The analysis of the results was used to determine the extent of time control in the construction project of the Juara Youth Building in Pangandaran Regency The purpose of this study is to determine time control using the Earned Value Management (EVM) method in the construction of facilities and infrastructure of the Pangandaran Regency Champion Youth Building. This study uses data that includes the location/location of the building, RAB calculation, S curve, time schedule, progress report. Based on the results of the project performance research in weeks 1, 2, 3, 4, 5, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, to 20 SV (Schedule Variances) values are positive (+) and the results of SPI calculations are more than one (>1). However, in the 6th week, 7,8,9 in the calculation of the value of the schedule variance (Schedule Variance) has a negative value (-) and the result of the SPI calculation is less than one (<1), This shows that for the SPI value that < 1 work experienced delays and SPI that >1 work experienced acceleration while the SPI equal to 1 work was equal to the plan.

Jurnal Ilmiah Teknik SipilVol. 2(1)
Universitas Galuh (ID)
Openalex Percentile: Top 75%
Value Engineering and Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.