Stochastic haul rate planning using two-stage stochastic programming and model predictive control

Abstract Optimising the scheduling of shovels and trucks is a critical task in open-pit mining, significantly impacting production efficiency and operational costs. Traditional models often assume ideal conditions without accounting for disturbances; however, in this paper, we address this gap by incorporating multiple uncertainties. These uncertainties are categorised into contingencies and variations. Contingencies are binary events that may or may not happen, such as shovel breakdowns. Variations are continuous factors such as fluctuations in mineral composition, truck travel time, maximum loading rate of shovels and maximum processing rate of crushers. We develop and test a robust mixed-integer programming (MILP) model for computing the optimal loading rate of shovels in open-pit mines. The problem is formulated as a two-stage stochastic optimisation problem which is then solved and executed in a receding horizon fashion. The proposed methodology is simulated for an open-pit mine in Australia’s Pilbara region and the results confirm the effectiveness of the proposed stochastic optimisation approach in minimising the effect of uncertainty on the operation.

Authors

Institutions

Publication Details

Journal
Optimization and Engineering
Published
2025-07-05
DOI
https://doi.org/10.1007/s11081-025-10002-3
Citations
1
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
1.21

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Stochastic haul rate planning using two-stage stochastic programming and model predictive control

Mohammadreza Chamanbaz, Konstantin M. Seiler, Stefan Trpkovski
1 citations
Optimization and Engineering
Mining Techniques and Economics
1.21
article

Stochastic haul rate planning using two-stage stochastic programming and model predictive control

Mohammadreza Chamanbaz, Konstantin M. Seiler, Stefan Trpkovski
article en
1 citations

Abstract

Abstract Optimising the scheduling of shovels and trucks is a critical task in open-pit mining, significantly impacting production efficiency and operational costs. Traditional models often assume ideal conditions without accounting for disturbances; however, in this paper, we address this gap by incorporating multiple uncertainties. These uncertainties are categorised into contingencies and variations. Contingencies are binary events that may or may not happen, such as shovel breakdowns. Variations are continuous factors such as fluctuations in mineral composition, truck travel time, maximum loading rate of shovels and maximum processing rate of crushers. We develop and test a robust mixed-integer programming (MILP) model for computing the optimal loading rate of shovels in open-pit mines. The problem is formulated as a two-stage stochastic optimisation problem which is then solved and executed in a receding horizon fashion. The proposed methodology is simulated for an open-pit mine in Australia’s Pilbara region and the results confirm the effectiveness of the proposed stochastic optimisation approach in minimising the effect of uncertainty on the operation.

Optimization and Engineering
University of Technology Sydney (AU), Australian Centre for Robotic Vision (AU)
University of Sydney, Australian Centre for Field Robotics
Openalex Percentile: Top 19%
Mining Techniques and Economics
1.21
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.