The Effective Analysis for East Karbala Diesel Power Station Photovoltaic System using Homer Pro Software

In Iraq, where electric generation is limited, a pilot work was conducted at East Karbala Diesel Power Station, in Karbala. This aimed to assess the implementation of PV solar systems on stations under both grid-connected and off-grid conditions. We will evaluate various factors, including net present cost, energy cost, operating and initial costs, and annual net energy consumption from the grid. The work analyzed various situations and considered the presence of backup generators (G1-250kVA) at the station. The first step is to conduct a walkthrough energy audit at EKDPS to determine the plant's load profile. By using HOMER Pro, further analysis is illustrated. Results indicated that integrating an on-grid PV system could reduce the cost of energy by 58%, making it the optimal situation when grid power is available. In this case, the Net Present Cost, operating cost per year, was $51,991. Conversely, in the absence of grid power, the best scenario involved a PV system with a 100-kWh lithium battery loading. Despite being the most effective resolution in this situation, the energy cost was 310% greater than the one-case energy rate in Iraq (0.1 $/kWh). Notably, both optimal scenarios did not require generators, highlighting a significant potential benefit for the Nero Zero system.

Authors

Publication Details

Journal
Journal of Engineering and Sustainable Development
Published
2025-07-01
DOI
https://doi.org/10.31272/jeasd.2530
Primary Topic
Energy and Environment Impacts
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The Effective Analysis for East Karbala Diesel Power Station Photovoltaic System using Homer Pro Software

Bashar J. Hamza, Mohanad Aljanabi, Haneen Flaih
Journal of Engineering and Sustainable Development
Energy and Environment Impacts
article

The Effective Analysis for East Karbala Diesel Power Station Photovoltaic System using Homer Pro Software

Bashar J. Hamza, Mohanad Aljanabi, Haneen Flaih
article en

Abstract

In Iraq, where electric generation is limited, a pilot work was conducted at East Karbala Diesel Power Station, in Karbala. This aimed to assess the implementation of PV solar systems on stations under both grid-connected and off-grid conditions. We will evaluate various factors, including net present cost, energy cost, operating and initial costs, and annual net energy consumption from the grid. The work analyzed various situations and considered the presence of backup generators (G1-250kVA) at the station. The first step is to conduct a walkthrough energy audit at EKDPS to determine the plant's load profile. By using HOMER Pro, further analysis is illustrated. Results indicated that integrating an on-grid PV system could reduce the cost of energy by 58%, making it the optimal situation when grid power is available. In this case, the Net Present Cost, operating cost per year, was $51,991. Conversely, in the absence of grid power, the best scenario involved a PV system with a 100-kWh lithium battery loading. Despite being the most effective resolution in this situation, the energy cost was 310% greater than the one-case energy rate in Iraq (0.1 $/kWh). Notably, both optimal scenarios did not require generators, highlighting a significant potential benefit for the Nero Zero system.

Journal of Engineering and Sustainable DevelopmentVol. 29(4)
Openalex Percentile: Top 89%
Energy and Environment Impacts
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.